COMMERCE BUSINESS DAILY ISSUE OF APRIL 17,2000 PSA#2580Department of the Treasury, Bureau of Engraving and Printing (BEP),
Office of Procurement, 14th & C. Streets, S.W., Washington, DC,
20228 95 -- FABRICATION OF TICKET BOOTH SOL BEP-00-21 DUE 042600 POC Gordon
Hackley, Contract Specialist, Phone (202) 874-2226, Fax (202)
874-2200, Email gordon.hackley@bep.treas.gov -- Denise Wright, Sup.
Contract Specialist, Phone (202) 874-2246, Fax (202) 874-2200, Email
WEB: Visit this URL for the latest information about this,
http://www.eps.gov/cgi-bin/WebObjects/EPS?ACode=P&ProjID=BEP-00-21
&LocID=142. E-MAIL: Gordon Hackley, gordon.hackley@bep.treas.gov.
This is a combined synopsis/solicitation for a Commercial Items
requirement prepared in accordance with Federal Acquisition Regulation
(FAR) Subpart 13.5, as supplemented with additional information
included in this notice. This acquisition is also being conducted in
accordance with FAR Part 15. This announcement constitutes the only
solicitation; a written solicitation will not be issued. Written
proposals are requested. This Request for Proposal (RFP) number is BEP-
00-21. This solicitation document incorporates provisions and clauses
that are in effect through Federal Acquisition Circular FAC 97-15. The
acquisition of the Ticket Booth is a 100% small business set-aside. In
accordance with FAR subpart 19.502-2(C), __any concern proposing to
furnish a product which it did not itself manufacture must furnish the
product of a small business manufacturer unless the Small Business
Administration has granted either a waiver or exception to the
nonmanufacturer rule._ This is a Firm Fixed Price Type contract. The
contractor shall CLIN 001 _ One Fabricated Ticket Booth as outlined in
the statement of work, specifications, and drawings. 1.0 SCOPE 1.1 The
Contractor shall provide all labor, materials, equipment, supplies,
specialty items and tooling, spares, and assembly. The Contractor shall
provide adequate crating for transportation to site allowing for the
replacement of the Bureau_s existing Ticket Booth, on the sidewalk
facing Raoul Wallenberg Place. The Contractor shall effect the project
design as described in the project drawings, specifications, except as
stated otherwise in this Statement of Work. 1.2 In case of conflicts
between the project specifications/drawings, and the Statement of Work,
the Statement of Work shall govern without exception. 2.0 DOCUMENTS 2.1
Applicable Documents: The Contractor shall comply with the current
editions of applicable building codes and standards as prepared by the
governing technical societies and associations. In case of conflict
between the codes and standards of those organizations, the more
stringent regulations shall govern. 2.2 Government Furnished Documents
The Bureau of Engraving and Printing (BEP) shall provide, as
attachments, the following: 1 Set of drawings, A1-A4, 1 Photograph of
National Capital Planning Commission Rendering, 1 Set of specifications
comprising Divisions 5,6,7,8,9,10. 3.0 REQUIREMENTS 3.1 The Contractor
is required to complete this contract within one hundred eighty (180)
calendar days and ship F.o.b. destination after contract award. 3.2
Milestone Dates: 3.2.1 The milestone dates stated herein are
requirements for this contract. 3.2.2 The Contractor shall submit the
Submittal Schedule within ten (10) calendar days after award of the
contract for approval by the Contracting Officer_s Technical
Representative (COTR). 3.2.3 Shop drawings, product data and samples
shall be submitted and approved by the COTR within thirty calendar
days. (Shop drawings, product data and samples shall be submitted
simultaneously to the COTR and the Architect/Engineer.) Any submittal
after this time frame will be processed in an expedited manner
according to an agreed upon schedule. The COTR will process the
submittal and either approve or provide comments to the Contractor
within seven (7) days after receiving each submittal. 3.2.4 The
Contractor shall submit a detailed schedule within ten (10) calendar
days after award of the contract. The schedule shall be prepared in
terms of calendar days (not working days). Once the schedule is
submitted by the Contractor and approved by the COTR, no deviation in
the schedule will be accepted unless approved by the Contracting
Officer and the COTR. 3.3 Quality Control: 3.3.1 The Contracting
Officer reserves the right to inspect the on site performance at any
time during the life of the contract. 3.3.2 Any omission or errors
caused by the Contractor shall be remedied immediately at no additional
cost to the BEP. The Contracting Officer shall make such notification
in writing. 3.3.3 All requests for information on the contract drawings
and/or specifications shall be made in writing. The BEP will respond
within five working days after receipt of the RFI. 3.3.4 Work not
included: Reference made, in the plans and specifications, to the site,
foundation system, and utilities required to make the Ticket Booth
fully operational are not-in-contract (nic). NOTE: The following
changes are made to the Drawings and Specifications: 3.4.1 A-3 The
ticket booth cross-section that shows the linear metal ceiling and
insulation as 3 12_ R-11 Batt Insulation shall be deleted as shown.
Additionally, references to batt insulation and interior metal cladding
finish; plastic laminate countertop shall be deleted. 3.4.2 A-2 West
Elevation indicates by note that the glass (2 units) to which the
speaker hole is mounted is _ 1_ Insulated Glass_ This note is deleted
and is superseded by the following: _ 14 inch tinted Tempered Glass_.
3.4.3 09900/4 C. Colors: para (1) Delete Sentence, and Replace with
_Apply paint manufactured by Pratt and Lambert, known as _Durango_#2284
whenever paint is specified or noted on the drawings and shown in the
Photograph to _match_ existing. All remaining exterior surfaces and
interior metal clad (wall) surfaces shall be painted with Benjamin
Moore, _HC166_. 4.0 GENERAL INFORMATION 4.1 The Contracting Officer
must approve all work beyond the scope of this contract before any
additional work can be started. Any additional work shall be performed
at the contractor_s expense. 4.2 Any administrative questions related
to this project shall be directed to the Contracting Officer, Mrs.
Denise P. Wright, CPCM at (202) 874-2246. After the award of this
contract, all technical issues shall be directed to the COTR, Joseph J.
Mancuso (202) 874-2296. Clauses/Provisions: FAR provision 52.212-1
_Instruction to Offerors-Commercial Items_ is hereby incorporated by
reference. The following are addenda to FAR Clause 52.212-1: Paragraph
(C) Period of acceptance of offers; The offeror agrees to hold the
prices in its offer firm for 60 calendar days from the date specified
for receipt of offers. FAR provision 52.212-2 _Evaluation-Commercial
Items_ applies to this solicitation and the following evaluation
criteria (arranged in order of importance) shall be used to evaluate
offers: 1) Conformance with specifications and drawings of the
fabrication of the ticket booth. 2) Past Experience _ Cast Iron and
Cast Aluminum Work own and operate a foundry, internal painting shop
and fabrications facility. Performed at least five projects of equal or
larger dollar value similar to the work of this project. Completed, or
be currently engaged in, at least three projects in the past twelve
months to provide cast ornamental metal for a building registered in
the National Register of Landmark Buildings. 3) Offeror_s Past
Performance. Technical evaluation points will be awarded on the three
evaluation factors. The offeror shall provide three references and
phone numbers for customers who have bought the same or similar
equipment. The offeror shall provide sufficient documentation and
narrative as to their experience (evaluation criteria #2) and past
performance (evaluation criteria #3). FAR provision 52.212-3 _Offeror
Representations and Certifications _ Commercial Items_ shall be
completed and submitted with the proposal. FAR clause 52.212-4
_Contract Terms and Condititions Commercial Items,_ applies to this
solicitation and includes the attached addenda (specifications and
drawings). FAR clause 52.212-5 _Contract Terms and Conditions Required
to Implement Statutes or Executive Orders-Commercial Items_ applies to
this acquisition. FAR clause 52.247-34 F.o.b. Destination applies to
this solicitation. CLIN 001 shall be delivered to the Bureau of
Engraving and Printing, 15th Street and Raoul Wallenberg Pl. S.W.
curbside north alley Washington, D.C. 20228-0001. Receiving hours for
deliveries are 7:00 a.m. to 3:00 p.m. local time, Monday through
Friday, excluding U.S. Government Holidays and BEP year-end-shutdown.
The contractor shall coordinate/schedule deliveries to the facility by
calling the COTR, Joe Mancuso on (202) 874-2296. The following
provisions for contract finance terms apply to this solicitation and
are included by addenda: an advance payment not to exceed 15% of the
contract price may be provided upon contract award; an interim payment
may be provided upon notification that the equipment is ready for
shipment; and the delivery payment on the balance will be made in
accordance with FAR clause 52.232.25 _Prompt Payment._ The Contracting
Officer may require additional security as prescribed in FAR 32.202-4
_Security for Government Financing._ However at a minimum the offeror
shall provide a statement with their proposal indicating additional
security will be provided if required. An official who can
contractually bind the company must sign the statement. All clauses can
be obtained in full text at the following web site:
http://www.arnet.gov/far/ . Proposals must be received not later than
April 26, 2000, 4:00 p.m. EST. Offers should be mailed to Bureau of
Engraving and Printing, Office of Procurement, Room 705A, 14th and C
Sts., S.W. Washington, D.C. 20228-0001, Attn: Gordon Hackley. If
proposals are faxed an original must be mailed to the above address.
See Numbered Note 1. Posted 04/13/00 (D-SN444858). (0104) Loren Data Corp. http://www.ld.com (SYN# 0353 20000417\95-0001.SOL)
95 - Metal Bars, Sheets and Shapes Index Page
|
|