COMMERCE BUSINESS DAILY ISSUE OF NOVEMBER 24,1999 PSA#2482Department of the Air Force, Air Force Space Command, 30CONS, Bldg
7015, STE 2D, 806 13th Street, Vandenberg AFB, CA, 93437-5226 Z -- ROOFING/WEATHERPROOFING IDIQ CONTRACT SOL F04684-99-R-0009 DUE
120999 POC Tyr Brenner, Contract Specialist, Phone 805.606.3872, Fax
805.606.4863, Email brennert@vafb5a.vafb.af.mil -- William Barron,
Contract Specialist, Phone 805.606.6692, Fax 805.922.1703, Email WEB:
Visit this URL for the latest information about this,
http://www.eps.gov/cgi-bin/WebObjects/EPS?ACode=M&ProjID=F04684-99-R-0
009&LocID=528. E-MAIL: Tyr Brenner, brennert@vafb5a.vafb.af.mil.
QUESTIONS AND ANSWERS TO PRE-PROPOSAL CONFERENCE HELD 18 NOV 99 Q1.
What does CLIN Item 0001AW, Material Pool mean? Will all delivery
orders have a fixed amount of Material Pool Dollars added or will it
only be on selected orders? If a roof-top HVAC unit is not up to code,
will we be required to replace the unit? A1. CLIN 0001AW will be used
on a case-by case basis (selected delivery orders) and will be used to
correct deficiencies to roof top equipment and systems that are not
incidental to the roofing process, but must be accomplished to complete
the project. Examples Include: replacement of a corroded conduit or
grounding clamp for a lightning rod; minor repair of deteriorated air
ducts, etc. Q2. Is CLIN item 0001BA and 0001BB intended to be used to
replace shrubs and plants that need to be removed to access work areas
or a vehicle to replace dead foliage? A2. CLIN item 0001BA and 0001BB
will be used to replace existing shrubs and plants with new plants and
shrubs that were removed to perform the work. Q3. In some CLINs the
word "install" is used; does this mean to furnish and install? A3. All
references to install, furnish, provide etc. shall be interpreted as
providing all material, labor, equipment, transporation etc. required
for a complete and useable end product. Q4. Specification section
01000, page 5, paragraph 1.11 C states: Transport unusable items to the
base landfill; 01000, page 7, paragraph 1.16 states: Transport unusable
items and trash off base. Do we use the base landfill or must all
unusable and trash items be transported to a municipal dump? A4. Refer
to specification section 01000, page 7, paragraph 1.16. Q5. Is it the
intent of specification section 02075, page 20, paragraph 3.21 to have
a Certified Industrial Hygenist (CIH) on site at all times during the
abatement process? A5. Refer to specification section 02075 page 07,
paragraph 1.12 E and page 20, paragraph 3.21. Q6. Specification section
02075, page 20, paragraph 3.22 states: Dispose of non-friable asbestos
off Government property. CLIN item 0018 states: Dispose of asbestos at
Vandenberg AFB landfill. Where do we dispose of asbestos containing
material? A6. Refer to CLIN item 0018. Q7. Where is abated lead based
paint disposed at, the base landfill or a lanfill off Vandenberg AFB?
A7. Refer to CLIN 0019 through 0019AE, specification section 02084,
09990 and 09991. Q8. What is the maximum dollar order of the job? A8.
Refer to Part 2, Section I, Contract Clauses, I-171, FAR Clause
52.216-19, Order Limitations. Q9. What is the minimum dollar value of
a single delivery order? A9. Refer to Part 2, Section I, Contract
Clauses, I-171, FAR Clause 52.216-19, Order Limitations. Q10. What is
the maximum dollar value to be awarded in the first year? A10.
Undetermined. Q11. Will there only be one contract award? A11. Yes.
Q12. Will there be a total square foot of roof for each roof type? A12.
Refer to contract Bid Schedule. Q13. How much sealed seam metal roofing
and roof coatings will there be? A13. Refer to contract Bid Schedule.
Q14. Will square footage be provided for foam roofing, coating, and
thickness in mils? A14. Refer to contract Bid Schedule. Q15. What type
of coatings are to be used? A15. Refer to contract Bid Schedule. Q16.
What type of specifications on metal type roofs. A17. Refer to
contract Bid Schedule and specifications. Q18. If a company has an
office in area 9, can a company with an office in the area, but who's
main office is in another area submit a proposal? A18. Yes, from SBA in
Los Angeles. Q19. Will sub-contracting be allowed or will you only be
bidding on what you are going to roof or what you want to roof? A19.
Yes, refer to clause 52.219-14 at I-221.. The prime contractor must
perfrom 25% of actual on site construction work ? Q20. How is past
performance evaluated and in what form should it be submitted? A20.
Refer to Part 4, Representations and Instructions, Section L-605B and
Evaluation Factors,Section M-7(2). Submit iaw L-603b and Appendix 1.
Q21. Do we propose on the base year only or base and option years? A21.
Base and option years as shown in L603.C(ii). All CLINs and SubCLINs.
Q22. How will cost be evaluated? A22. The aggregate of the base and all
option years. See L603c(ii) and M-7. Posted 11/22/99 (D-SN402794).
(0326) Loren Data Corp. http://www.ld.com (SYN# 0096 19991124\Z-0004.SOL)