COMMERCE BUSINESS DAILY ISSUE OF AUGUST 2,1999 PSA#2400USDA Forest Service, Sierra National Forest, 1600 Tollhouse Road,
Clovis, CA 93611-0532 Y -- LOWER GRANITE TRAIL BRIDGE SOL IFB R5-15-99-51 DUE 091699 POC
Mike Angove, (559) 297-0706 Extension 4844 or Patrick Gallegos, (559)
297-0706 Extension 4830 This project work, located on the Minarets
Ranger District, Sierra National Forest, consists of the Installation
of a 90-foot Steel Girder Bridge with Concrete Footings. Work consists
of excavation, Bridge Footing construction, installation of Steel
Girder bridge including guard railing and decking. The estimated start
work date is November 1, 1999. The estimated contract time is 90 days.
The estimated price range is between $100,000 and $250,000. There will
be a charge of $25.00 for plans and specifications. Posted 07/29/99
(W-SN360838). (0210) Loren Data Corp. http://www.ld.com (SYN# 0153 19990802\Y-0017.SOL)
Y - Construction of Structures and Facilities Index Page
|
|