COMMERCE BUSINESS DAILY ISSUE OF MAY 13,1999 PSA#2345Defense Supply Center Columbus, PO Box 16595, DSCC-PBAB, Columbus, OH
43216-6595 59 -- DUMMY LOAD, ELECTRICAL SOL SP0920-99-R-A110 DUE 070299 POC Susan
Bland/CSFLK/(614) 692-8517 E-MAIL: Defense Supply Center Columbus --
Contract Specialist, susan_bland@dscc.dla.mil. PR. No.: YPE99007000149.
NSN: 5985-01-208-5481. Dummy Load, Electrical. No waived sources for
First Article Testing. 2 ea. to be delivered to Ellsworth AFB, SD
within 120 days. Various increments solicited: 1-4, 5-9, 10-24, 25-49.
Full and open competition applies. See notes 1, 22, and 26. Copies of
this solicitation are available at the address above. The small
business size standard is 750 employees. Applicable documents:
MIL-PRF-39030C, 1 Aug 97, Amend 1, 7 Jul 98. MIL-D-39030/7, 22 Dec 80,
Amend 1, 6 Aug 97. And all associated documents as called out by the
aforementioned documents. Acceptance testing shall be performed IAW:
Paragraphs 4.5 thru 4.5.1.2.1 of MIL-PRF-39030. Sampling plan shall be
IAW paragraph 4.5.1.2.1 of MIL-PRF-39030. Preproduction Testing is
required. First Article Contractor Testing IAW Paragraph 4.4 thru 4.4.2
of MIL-PRF-39030C, as amended, as applicable. Special Provisions for
First Article Requirements: Test Reports and Samples/Evaluation and
Approval: Send test reports to:DSCC-VQ. First Article samples are to be
retained by the contractor and disposed of as follows: Four (4) samples
will be retained as production standards but shall not be submitted for
acceptance as part of the order quantity. Conditions for Waiver of
First Article Testing: The government reserves the right to waive the
requirements for first article testing for those offerors of a product
which: Has been previously accepted by the government and has not been
found to be unsatisfactory. Has previously met the preproduction
testing requirements, been accepted by the government and has not been
found to be unsatisfactory. First Article Approval -- Contractor
Testing: The contractor shall test (4) units of Lot/Item as specified
in this contract. Estimated test time is (60) days. Sixty (60) days
will be required for preproduction test review. (Does not include
mailing time). This solicitation includes "Options for Increase
Quantity" clause (I-37). Posted 05/11/99 (W-SN329921). (0131) Loren Data Corp. http://www.ld.com (SYN# 0307 19990513\59-0007.SOL)
59 - Electrical and Electronic Equipment Components Index Page
|
|