COMMERCE BUSINESS DAILY ISSUE OF MARCH 4,1999 PSA#2295Alliant Techsystems Incorporated, Allegany Ballistics Laboratory, P.O.
Box 210, State Route 956, Rocket Center, WV 26726 Y -- SUBSTATION UPGRADE SOL PHC-272 POC Patrick H. Cunningham,
304-726-5047 The work consists of installing a new 10,000 KVA, 34,500V
to 7,200V transformer, installing new 34,500 voltage regulators,
building new sieel structures for the air break switches, fused
disconnects, and related equipment to be mounted. Also pertaining to
this would be installing related conductors to an existing 7200V
structure. Bid date is not firm, but will be on or after April 22,
1999. Estimated range is between $200,000 and $300,000. Bonds will be
required. West Virginia Contractors License must be submitted prior to
the commencement of work by the Contractor and all lower-tier
Subcontractors. In order to obtain plans and specifications, please
submit a $35 non-refundable fee payable to Alliant Techsystems with a
written request. Alliant reserves the right to refuse written requests
for plans and specifications on/after March 22, 1999. Posted 03/02/99
(W-SN303605). (0061) Loren Data Corp. http://www.ld.com (SYN# 0088 19990304\Y-0002.SOL)
Y - Construction of Structures and Facilities Index Page
|
|