COMMERCE BUSINESS DAILY ISSUE OF DECEMBER 15,1998 PSA#2242USAFE Contracting Squadron/LGC, Unit 3115, APO AE 09094-3115 61 -- UNINTERRUPTIBLE POWER SUPPLY AND BATTERY SYSTEM SOL
F61521-99QG230 DUE 011499 POC Anja Steil, Contract Buyer
(011-49-631-3539-206) E-MAIL: UNINTERRUPTIBLE POWER SUPPLY AND BATTERY
SYSTEM, ANJA.STEIL@RAMSTEIN.AF.MIL. UNINTERRUPTIBLE POWER SUPPLY
SYSTEM,TO BE REMOVED, DISPOSED DELIVERED AND INSTALLED; VOLTAGE: IN AND
OUTPUT: 380 VAC, 50 HZ; MAXIMUM DIMENSIONS: H=2000 MM, W=2000 MM,
D=1000 MM; CONSISTING OF THE FOLLOWING COMPONENTS: 2 UNITS; RECTIFIER,
MIN.6 PULSE, FOR EACH UNIT, INCLUDING A INPUT FILTER AND A DC FILTER
FOR OUTPUT; INVERTER FOR EACH UNIT; STATIC BY-PASS FOR EACH UNIT,
PARALLEL ELECTRONIC FOR EACH UNIT; REMOTE PANEL FOR EACH UNIT; INTERNAL
MAINTENANCE BY-PASS INPUT FOR EACH UNIT; ENCLOSURE CABINET FOR EACH
UNIT; WITH THE THE FOLLOWING REQUIREMENTS: SHALL HAVE CONTINUOS POWER
TO LOAD WITHOUT INTERRUPTION; SHALL BE CONFIGURED TO SHARE THE LOAD
EQUALLY;SHALL HAVE A MAX. CAPACITY OF 200 KVA; SHALL CONTAIN THE IGBT
TECHNOLOGY; SHALL BE SHOCK PROOFED IN ACCORDANCE WITH THE SEISMIC ZONE
2A, BATTERY SYSTEM, TO BE REMOVED, DISPOSED, DELIVERED AND INSTALLED;
MAX. DIMENSIONS: H=1500 MM, W=3000 MM, D=490 MM; CONSISTING OF: 2
SEPERATE BANKS; WITH A MIN. NEED OF 100 KVA FOR A 15 MINUTE BACK-UP
TIME; WITH THE FOLLOWING REQUIREMENTS: SHALL BE CLOSED AND MAINTENANCE
FREE; HAVE HAVE 10 YEAR LIFE TIME, VALVE REGULATED LEAD ACID TYPE;
SHALL BE FLAME RETARDING; SHALL BE CHARGED; SHALL BE CONNECTED TO THE
RESPECTIVE UPS SYSTEM; SHALL HAVE A LOADING TEST-CERTIFICATE, TO SHOW
THAT EACH BATTERY IS PERFORMING PROPERLY; SHALL HAVE SCREWED AND
SECURELY CONNECTED BATTERY POLES IN ACCORDANCE WITH THE BATTERY SYSTEM;
WITH USER OPERATOR MANUAL AND ON SITE OPERATOR TRAINING, ENGLISH
LANGUAGE, NOTE: THE CONTRACTOR SHALL NOT REMOVE THE EXISTING POWER
SUPPLY AND BATTERY SYSTEM AT THE SAME TIME, WHEN THE NEW EQUIPMENT WILL
BE DELIVERED AND INSTALLED. THE CONTRACTOR SHALL NOT REMOVE NOR DISPOSE
THE EXISTING PLATE OF THE UPS AND BATTERY SYSTEM, BECAUSE THE NEW UNITS
SHALL BE MOUNTED TO. FOR THE PHASE OF THE INSTALLATION, VENDORS ARE
ALLOWED TO USE THE EXISTING CABLES, HOWEVER THE INPUT CIRCUIT BREAKERS
MUST BE SIZED IN ACCORDANCE WITH THE DELIVERED UPS SYSTEM. IF THE
DELIVERED CIRCUIT BREAKERS ARE LARGER THAN THE EXISTING FRAMES, THE
FRAMES SHALL ALSO BE REPLACED IAW SINGLE LINE DIAGRAM. THE CONTRACTOR
MUST PERFORM A SITE VISIT AT THE LOCATION PRIOR TO START OF
PERFORMANCE, DELIVERY: FOB DESTINATION TO RAMSTEIN AIR BASE. REQUEST
FOR QUOTATION WILL BE MADE AVAILABLE FROM THE USAFE CONTRACTING
SQUADRON HOME PAGE: http://www.usafe.af.mil/joint/cons Posted 12/11/98
(W-SN279410). (0345) Loren Data Corp. http://www.ld.com (SYN# 0256 19981215\61-0013.SOL)