COMMERCE BUSINESS DAILY ISSUE OF NOVEMBER 3,1998 PSA#2214Bureau of Reclamation, PO Box 36900, Billings, Montana 59107-6900 Z -- FRESNO BOATRAMP AND PARKING LOT REPAIR, MILK RIVER PROJECT,
MONTANA SOL 99-SI-60-0300 DUE 121698 POC Hart BlackEagle, 406/247-7803
or Dean Cave 406/247-7646 E-MAIL: Hart BlackEagle at the Great Plains
Regional Office, hblackeagle@gp.usbr.gov. The work consists of: (1)
moving approximately 100 cubic yards of fallen rock from the alignment;
(2) excavating a 2' wide trench, 4' deep, 190' in length in compact to
weakly cemented, fine grained friable sandstone along the base of the
eroding parking lot slope; (3) placing sheet steel piling in the
trench extending above the trench 10' to 16', level with the elevation
of the asphalted parking lot surface; (4) placing geotextile fabric in
the trench and extending it 10' down slope of the trench; (5)anchoring
the sheet piling and geotextile edge in the trench with concrete; (6)
covering the geotextile with 4" of concrete reinforced with 6" X 6"
welded wire fabric; (7)placing the removed rock on this concrete apron
against the toe of the piling and slush-grouting it in place; (8)
backfilling the void area between the eroded slope and the sheet piling
with concrete in at least 4 lifts, with 24 hours minimum between lifts,
to match the grade of the existing parking lot asphalt surface.
Restraint and tieback of the piling during backfill concreting will be
required, and the backfill side of each sheet of the piling will have
12" long stud welded or through-bolted anchors at each lift to prevent
the piling from separating from the backfill concrete. (9) A 40' length
of the eroded area, which extends past the trenched alignment, will
have 5' to 10' lengths of steel sheet piling concreted in place at the
top of the existing rock rubble slope and backfilled with concrete to
the elevation of the parking lot asphalt surface. The rock rubble
foundation under the backfill concrete will be neat-cement grouted
prior to placing backfill concrete. (10) The existing parking lot
guardrail posts and guardrail which have eroded out in one area will be
raised in place and supported to the original installed elevation and
concreted in place during the final concrete backfill lift. The edge of
the existing asphalt surface will be trimmed to a uniform line
paralleling the sheet pile alignment and the final concrete lift will
match the edge of the asphalt surface. (11) A layer of local rock (18"
minus) will be placed on the surface of the freshly placed final
concrete lift, extending 4' back from the edge of the sheet piling,
along the length of the repaired area. Posted 10/30/98 (W-SN267129).