COMMERCE BUSINESS DAILY ISSUE OF JUNE 19,1998 PSA#2120U. S. Army Corps of Engineers, Omaha District, 215 North 17th Street,
Omaha, NE 68102-4978 Y -- BANK EROSION PROTECTION, LAFRAMBOISE BACKWATER AREA, PIERRE,
SOUTH DAKOTA SOL DACW45-98-B-0052 DUE 073098 POC Contract Specialist:
Bob Cooper, 402-221-4102 WEB: Omaha District Contracting Division
Homepage, http://ebs.nwo.army.mil./EBS/CONTRACT.HTM. E-MAIL: Bob Cooper
or Sue Sharman, Bob.Cooper@usace.army.mil or
Sue.A.Sharman@usace.army.mil. On or about 30 June 1998, this office
will issue Invitation for Bids for the construction of BANK EROSION
PROTECTION, LAFRAMBOISE BACKWATER AREA, PIERRE, SOUTH DAKOTA. Bids will
be opened on or about 30 July 1998. This solicitation is unrestricted
and open to both large and small business participation. Contractors
interested in inspecting the site of the proposed work should contact
the Project Manager's Office, Oahe Project, U.S. Army Corps of
Engineers, P.O. Box 997, Pierre, South Dakota 57501, Telephone (605)
224-5862 ext 3100. FAX (605) 224-5945.The work will include the
following: (Approx. quantities)4,300 tons of Rirap; 2,100 tons granular
bedding; and 2,600 square yards of filter fabric. The estimated
construction cost of this project is between $100,000 and
$250,000.Contractor's Quality Control will be a requirement in this
contract.Large business concerns submitting bids for services exceeding
$500,000 or for construction exceeding $1,000,000, shall comply with
Federal Acquisition Regulation 52.219-9 regarding the requirement for
a subcontracting plan. The U.S. Army Corps of Engineers considers the
following goals reasonable and achievable for fiscal year 1998:(a)Small
Business: 61.2% of planned subcontracting dollars.(b)Small
Disadvantaged Business: 9.1% of planned subcontracting dollars.(c)Women
Owned Small Business:4.5% of planned subcontracting dollars.The
Contractor will be required to commence work within 10 days after
notice to proceed and complete the work 90 calendar days after receipt
of Notice to Proceed. Provisions will be included for liquidated
damages in case of failure to complete the work in the time allowed.
Performance and payment bonds will be required.Plans and Specifications
will be provided free of charge. All requests for solicitation packages
should be made in writing and no later than 14 days prior to bid
opening. After such time, packages will be furnished if supply is
available. It has been determined that the number of sets be limited to
one (1) per firm.Ordering of plans and specifications shall be by
written request or register on the Omaha District website:
http://ebs.nwo.usace.army.mil/EBS/Contract.htm or faxed to (402)
221-4530 with the following information:1)Name of Firm; 2)Point of
Contact; 3)Mailing Address;4)Street Address for Parcel Delivery
Service;5)Telephone and Fax Phone Numbers with Area Code (FAX numbers
are mandatory to ensure the receipt of any amendments that may be
faxed);6) Level of Participation (General Contractor, Subcontractor,
Supplier or Plan Room); and7)Large Business, Small Business or Small
Disadvantaged Business.If any of the information changes during the
advertisement period, submit the information via e-mail to
Bob.Cooper@usace.army.mil or Sue.A.Sharman@usace.army.mil or by written
request or fax. Failure to provide the above information and any
changes may cause a delay in receiving plans, specifications and
amendments. Questions regarding the ordering of same should be made to:
402-221-4102 or 3527. Telephone calls regarding Small Business matters
should be made to: 402-221-4110. Telephone calls on contents of
drawings and specifications should be made to Specification Section at:
(402) 221-4413. (0168) Loren Data Corp. http://www.ld.com (SYN# 0123 19980619\Y-0009.SOL)
Y - Construction of Structures and Facilities Index Page
|
|