COMMERCE BUSINESS DAILY ISSUE OF MAY 27,1998 PSA#2103U.S. ARMY CORPS OF ENGINEERS, ROOM 324, FEDERAL BLDG. 334 MEETING ST.,
CHARLESTON, SC 29403 Y -- TURKEY CREEK FLOOD CONTROL PROJECT, CITY OF SUMTER, SUMTER
COUNTY, SOUTH CAROLINA SOL DACW60-98-B-0011 DUE 071898 POC Contract
Specialist Barbara J. Barnette (803) 727-4220 (Site Code DACW60)
PRESOLICITATION NOTICE -- DATES ARE APPROXIMATE. TO BE ISSUED BY CD
ROM. Furnish all labor, equipment and material for excavating soil
material from canal and depositing the soil material into designated
disposal areas. Work associated with this effort are construction of a
102 inch diameter steel tunnel liner pipe, demolition, fencing and
erosion control. Summary of work for all sites are: tunnel liner pipe
approx. 85 LF; clearing and grubbing approx. 1.30 acres; excavation
approx. 6600 CY; erosion control approximately 2.00 acres and 790 LF of
fencing. The estimated value of the work is between $500,000 and
$1,000,000. Plans and specifications are no charge. Mail request to
U.S. Army Corps of Engineers, PO Box 919, Charleston, SC 29402-0919,
Charleston, SC 29402-0919, Attn: Contracting Dept. Telephone requests
will not be honored. SICC is 1629. Size standard is $13.5 million.
(0142) Loren Data Corp. http://www.ld.com (SYN# 0136 19980527\Y-0023.SOL)
Y - Construction of Structures and Facilities Index Page
|
|