COMMERCE BUSINESS DAILY ISSUE OF MAY 19,1998 PSA#2098JACKSONVILLE DISTRICT OFFICE, U.S. ARMY CORPS OF ENGINEERS, P.O. BOX
4970, JACKSONVILLE, FL 32232-0019 Y -- RIO PUERTO NUEVO CHANNEL PROJECT, CONTRACT 2A, PUERTO RICO SOL
DACW17-98-B-0015 DUE 073198 POC Contract Specialist Robert Mosteller
(904) 232-3739 (Site Code DACW17) This work entails the excavation of
the Rio Puerto Nuevo main channel from STA. 62+00 to STA. 88+26 and the
Margarita Tributary from STA. M 0+00 to STA. M 51+50. The following
features are included in Contract 2A BASE BID: (a) Pipe pile wall
system on the west side of the channel from STA. 64+00 to STA. 74+32.5;
(b) Pipe pile wall system on the east side of the channel from STA.
64+00 to STA. 74+32.5; (c) Phase II of the SAN Jose Trunk Sewer
Siphon/Waterline Relocation which includes the construction of influent
and effluent siphon structures, a downstream diversion structure,
connecting RCP, waterline air release valves, connecting DIP and HDPE,
transitions, and appurtenances; (d)Dredging of a trapezoidal earth
channel with ocean disposal of the Puerto Nuevo Channel from STA. 62+00
to STA. 88+26, the Margarita Channel from STA. M 0+00 to STA. M 22+00,
and the Margarita Channel from STA. M 37+00 STA. M 51+50; (e) Dredging
of a trapezoidal earth channel with upland disposal of the Margarita
Channel fromSTA. M 22+00 to STA. M 37+00; (f) Sheet pile with concrete
facing wall at the Margarita/Puerto Nuevo Confluence from Margarita
STA. M 0+00 to STA. M 4+00 and Puerto Nuevo Transition Channel STA. T1
0+00 to about STA. T1 3+66; (g) Excavation and grading of mangrove
planting mitigation areas; and (h) lateral load tests. OPTIONAL BID
ITEM A is also part of Contract 2A and includes Phase I of the San Jose
Trunk Sewer Siphon Relocation consisting of the upstream diversion
structure and connecting RCP. The option work, if exercised, is to be
performed concurrently with the San Jose Trunk Sewer Siphon/Waterline
Relocation construction of the BASE BID. No additional time will be
added to the contract period of performance. PLEASE NOTE: BASE BID --
1,095 calendar days after receipt of NTP; OPTIONAL BASE ITEM A -- To
run concurrently with the Sewer Siphon Work (first order of work) is
Base Bid; no additional time will be added. Magnitude of construction
is more than $10,000,000. Pre-Solicitation Notice will be issued on or
about 13 May 98. Invitation DACW17-98-B-0015 will be issued on or
about 15 June 98 and opened on or about 31 July 98. Cost of Plans and
Specifications is $105.00. Checks should be made payable to FAO USAED
Jacksonville, and sent to U.S. Army Corps of Engineers, Jacksonville,
Florida. THIS IS AN UNRESTRICTED ACQUISITION. NOTE: Contracting
information for the Jacksonville District is now available at our web
site: (0135) Loren Data Corp. http://www.ld.com (SYN# 0114 19980519\Y-0016.SOL)
Y - Construction of Structures and Facilities Index Page
|
|