|
COMMERCE BUSINESS DAILY ISSUE OF APRIL 8,1998 PSA#2069Bureau of Reclamation, Contracts Group, 1150 N. Curtis Road, Suite 100,
Boise, Idaho 83706-1234 61 -- GENERATOR FIELD WINDING REINSULATION SOL 1425-98-SQ-00950 POC
Terry Ford (contracting) 208-378-5100; Terrald Kent (technical)
208-378-5290 E-MAIL: click here to contact the contracting officer via
e-mail, tford@pn.usbr.gov. The Bureau of Reclamation's Pacific
Northwest Regional Office (Reclamation) proposes to make a sole-source
award (using Federal Acquisition Regulation [FAR] Part 12 commercial
item procedures) to the General Electric Company's Salt Lake City,
Utah, component for the following remanufactured items: removal,
re-insulation, and reinstallation of field windings from the Green
Springs Powerplant (fifteen miles southeast of Ashland, Oregon)
generator's field pole pieces. The insulation on the windings has
deteriorated to the point that the windings must be reinsulated to
obtain the necessary resistance readings required for operation.
Reclamation will remove the pole pieces and field windings from the
generator rotor for shipment to the contractor's facility approximately
April 27, 1998. The reinsulated windings must be returned and ready for
re-installation by the Government no later than May 15, 1998.
Evaluation factors for award will be performance time, technical
capability, and price. Reclamation is preparing specifications and
expects to issue the solicitation, including more detailed information
about the evaluation for award process, around April 10, 1998. Unless
the solicitation includes drawings, it will be available
electronically as well as in written form. While all responsible
sources may submit a quotation which will be considered, at present the
only known source capable of meeting the Government's needs and
returning the re-insulated field windings in the shortest possible time
is the General Electric Company's Salt Lake City, Utah component. The
proposed lack of competition is justified, pursuant to 41 U.S.C.
253(c)(2), ["unusual and compelling urgency"] for the following
reasons: First, to move water from the high storage reservoirs down to
the irrigation distribution system, Reclamation must either operate
the Greensprings Powerplant or run water down a wasteway channel into
Tyler Creek. However, due to the severely deteriorated condition of the
insulation on the field windings, operation of the Greensprings
Powerplant in its existing condition creates an unacceptable risk of
catastrophic destruction of the generator if the insulation should fail
during operation. Therefore, our only alternative is to operate the
wasteway. Second, however, operation of the wasteway is quite costly,
as it results in damage to Tyler Creek for as long as the wasteway
continues to operate. The damages from a past extended operation have
generated claims which are not yet all settled. Reclamation has not yet
been able to perform wasteway channel improvement activities to prevent
additional damage from occurring in future wasteway operations. The
costs of the damage to the wasteway channel can be broadly estimated
from claims that resulted from its last prolonged operation. These
claims were for loss of land (areas which were made unusable due to
erosion of the channel banks), loss of timber (trees which were
destroyed due to erosion and sloughing of the channel banks), and loss
of value of land (due to access difficulties resulting from the newly
eroded channel). These claims were initially for millions of dollars.
While a settlement is near, it has not been finalized, and therefore
amounts cannot be specified exactly. It appears that the final cost to
the Goverment will be in the range of $100,000 to $150,000. Any new
costs attributable to additional loss of land and timber will probably
increase in direct proportion to the duration of wasteway operation,
while the loss of land value may not be as directly related to
duration. In any case, extended operation will increase costs. Third,
the Government will suffer further injury from operating the wasteway
arising from the loss of water storage capacity in Emigrant Reservoir,
due to material eroding from the wasteway and coming to rest in the
reservoir. The costs of lost storage in Emigrant Reservoir are
difficult to quantify, but it is certain that the useful life of
Emigrant Dam has been shortened, and would be further shortened by
unneccessary operation of the spillway WASTEWAY?. Fourth, there will be
a loss of revenue from foregone power generation. That revenue can be
estimated fairly precisely from past operation, and will be about
$11,000 a week. Requests for solicitation may be made to: Terry K.
Ford, Jr., by mail at the above listed address, by e-mail at
tford@pn.usbr.gov, and by fax at (208)-378-5108. (0094) Loren Data Corp. http://www.ld.com (SYN# 0211 19980408\61-0002.SOL)
61 - Electric Wire and Power and Distribution Equipment Index Page
|
|