COMMERCE BUSINESS DAILY ISSUE OF MARCH 10,1998 PSA#2048Portsmouth Naval Shipyard, Facilities and Maintenance Department, Bldg.
237, Code 914VC, Portsmouth, NH 03804-5000 C -- MARINE ENGINEERING SERVICES -- 1999 SOL N62472-98-D-6520 DUE
041498 POC Point of Contact-Vivian A. Carignan, Contract Specialist,
(207)438-5549 E-MAIL: Portsmouth Naval Shipyard,
vac_c910@ports.navy.mil. Scope of Services: Architectural and
engineering services at the Portsmouth Naval Shipyard, Kittery, ME for
an indefinite quantity contract for the preparation of contract
drawings, specifications prepared using the SPECSINTACT system, design
analyses, cost estimates, and AutoCAD compatible disks. Post
construction award options such as shop drawing review/approval,
consultation during construction and Title II inspection may be
included. There will be no dollar limit per project. The total fee that
may be paid under this contract (including one option year) will not
exceed $1,000,000. The duration of this contract will be for one year
from the date of the initial contract award with an option for one
additional one-year period which may be exercised at the discretion of
the Government subject to workload and/or satisfaction of A/E
performance under the subject contract. Asbestos/lead paint may be
encountered during design of all projects under this contract. The
Government will perform all sampling and testing of these materials and
provide all technical specifications required. The A/E shall identify
these areas on contract drawings, quantify the removals required, and
retain the services of an Industrial Hygienist if necessary to assist
in the preparation of cost estimates. Initial Project: Provide
professional marine engineering services for the preparation of
contract drawings, specifications using the SPECSINTACT system, design
analysis, cost estimates, and AutoCAD compatible disks to structurally
repair Berth 11 which is a reinforced concrete deck / pile cap
supported by steel H-piles, and replace the existing fender system at
Portsmouth Naval Shipyard, Kittery, ME. Design support services will
include civil, mechanical, electrical, and potentially architectural
work. SF254/255 package must clearly address all of these design
support services. This initial project will be the guaranteed minimum
for this contract. Follow-on design projects, which may be added to the
contract for a period of one year from the date of award, may include,
but not be limited to, repairs to timber wharves, quay walls, and
sheet pile cellular cofferdams, and other marine related work.
Significant Evaluation Factors (in order of importance): (a)
qualifications and recent experience of people (including on staff
and/or subconsultant divers) with respect to repairing marine
structures, (b) past performance with respect to quality of work and
compliance with performance schedules and cost constraints, (c)
location of the firm in the general geographical area of the project
and knowledge of the locality, (d) past experience, if any, with
respect to performance on Department of Defense contracts, (e) present
workload and ability to accomplish work within the required time
frame, (f) demonstrated success in prescribing the use of recovered
materials and achieving waste reduction and energy efficiency in
facility design, (g) extent of participation of small businesses,
including small disadvantaged businesses, historically black colleges
and universities, and minority institutions on the proposed contract
team as measured as a percentage of the estimated effort, and (h)
volume of work awarded by the Department of Defense within the last 12
months. Contract No.: N62472-98-D-6520 (number must be cited on SF
255) Type of Contract: Firm Fixed Price. Estimated Start Date: Oct
1998. Estimated Completion Date: Oct 1999. Estimated Cost of
Construction: $50,000 -- $6,000,000 Per Project. A/E firms which meet
the requirements described in this announcement are invited to submit
complete, updated SF 254 and SF 255 forms. One copy of each form must
reach Code 914VC by 3:00 PM on 14 April 1998. No material will be
returned. Clearly show qualifications, relative experience, and office
location of the Project Manager and key individuals who will be
assigned to this contract, including those who will be providing design
support services. If the Government Board cannot clearly identify the
key individuals who will be assigned to this contract, the firmwill not
be short listed. Specifically address each significant evaluation
factor listed above. This is not a request for proposal. See Note 24.
(0065) Loren Data Corp. http://www.ld.com (SYN# 0026 19980310\C-0004.SOL)
C - Architect and Engineering Services - Construction Index Page
|
|