COMMERCE BUSINESS DAILY ISSUE OF AUGUST 15,1997 PSA#1910U.S. ARMY CORPS OF ENGINEERS, TRANSATLANTIC PROGRAMS CENTER, P. O. BOX
2250, WINCHESTER VA 22604-1450 Y -- SPARE PARTS MAIN DEPOT STORE 63, CAIRO, EGYPT SOL
DACA78-97-R-0031 DUE 112597 POC Contract Specialist Steve Ritter (540)
665-3784 (Site Code DACA78) SPARE PARTS MAIN DEPOT STORE 63, CAIRO,
EGYPT SOL DACA78-97-R-0031 DUE 112597 POC Contract Specialist Steve
Ritter (540) 665-3784 (Site Code DACA78) The purpose of this
announcement is to solicit names of construction firms or joint
ventures interested in submitting an offer for this project. Eligible
contractors will be limited to (1) U. S. construction firms (2) joint
ventures between U. S. firms with at least one U. S. construction firm
or (3) joint ventures between U. S. firms and Egyptian firms,
including at least one U. S. construction firm. To be considered a U.
S. construction firm, the firm must perform construction as a
significant portion of its business; must be incorporated and have its
corporate headquarters in the U. S.; must have paid corporate
franchise and employment taxes in the U. S. for a minimum of two years
and shall have filed state and federal income tax declaration for a
minimum of two corporate years, having paid any applicable taxes
determined to be due as a result of such filings; and employ U.S.
citizens in key management positions. To be considered an Egyptian
firm, the firm must be a minimum of fifty-one percent Egyptian
ownership, and an independently-owned firm. Firms which are partially
or wholly owned by, or otherwise affiliated with the Government of
Egypt or its agencies are ineligible. Performance guarantees will be
required. The estimated cost of construction is between two and five
million dollars. PROJECT SCOPE. At a facility, which serves as a
receiving, warehousing, and shipping point for military material for
the Ammunition and Armament Department of the Egyptian Land Forces,
construct four (4) buildings: Receiving Warehouse, a metal panel
building with CMU skirt walls and three (3) other buildings, Contract,
Personnel Support, and Generator, are concrete frame buildings with
CMU fill-in walls and stucco construction. Total building area is
approximately 784 square meters. Building furniture and furnishings
will be provided, as well as some ventilation and air conditioning.
Site work will include grading, paving, sanitary, water, electrical,
and communication systems. Work also includes upgrading an existing
cave used to store materials. PLANS AND SPECIFICATIONS: The plans and
specifications will be available only to prime construction contractors
at no charge. There will be a charge for interested subcontractors and
suppliers. CONTRACT PROCEDURES: Both a technical and price proposal
will be required. Award will be made to the responsible offeror with
the lowest priced, technically acceptable proposal. Technical
acceptance of a proposal shall be determined on pass/fail of specific
technical evaluation factors. The technical evaluation factors will be
categorized into three basic groups: (1) Offerors Experience, (2)
Offerors Past Performance, and (3) Offerors Management and Execution
Plan. Request for Proposal (RFP) will be issued to construction
contractors responding to this notice. Tentative date for issuance of
RFP is 26 September 1997. Tentative date for receiptof proposals is 25
November 1997. Tentative construction award date is 18 December 1997.
Tentative construction period is 15 months. NOTE: Firms interested in
receiving this solicitation should send a written request to either
the address listed above, or fax a copy to (540) 665-4033. The request
should state the name of the company, mailing and shipping addresses
of the firm, telephone and fax numbers, point of contact, and should
reference the solicitation number. (0225) Loren Data Corp. http://www.ld.com (SYN# 0158 19970815\Y-0009.SOL)
Y - Construction of Structures and Facilities Index Page
|
|