COMMERCE BUSINESS DAILY ISSUE OF JULY 14,1997 PSA#188662D Contracting Squadron, 100 Main Street, Suite 1049, McChord AFB, WA
98438-0178 Z -- REPAIR LEAN TO HANGARS 1, 2, 3 & 4 SOL F4560397B8011 DUE 082797
POC SSgt Glass, (253) 984-2534 or by fax, (253) 984-5207/5053 The work
covered in these specifications consists of furnishing all plant,
labor, equipment and materials ( except government-furnished materials)
for the construction work at McChord AFB, WA. The contractor is
responsible for accomplishing all items of work accordance with the
applicable drawings, specifications and provisions of the contract. Any
sundry labor, materials, euipment and/or appurtances not specifically
detailed or specified, but required to complete the project, shall be
provided as an integral part of the scope of work hereinafter
specified. The following items are a brief summary of the project
revealing the general nature of the work involved. 1.1 Repair Lean To
Hangars 1and 2, work includes but is not limited to the following:
1.1.1 Repair/Replacemnt of exterior doors & frames 1.1.2 Install new
free standing metal canopies at designated exits 1.1.3 Replacement of
exterior windows new historically simulated anodized aluminum. 1.1.4
Cleaning and repair of brick masonry 1.1.5 Modify and/or provide new
T-bar acoustical ceiling tile at interior spaces adjacent exterior
walls where transition of suspended ceiling occurs at new windows.
1.1.6 Install concrete ramp for the handicapped 1.2 Repair Lean To
Hangars 3 and 4, work includes but is not limited to the following:
1.1.1 Repair/Replacemnt of exterior doors & frames 1.1.2 Install new
free standing metal canopies at designated exits 1.1.3 Replacement of
exterior windows new historically simulated anodized aluminum. 1.1.4
Cleaning and repair of brick masonry 1.1.5 Modify and/or provide new
T-bar acoustical ceiling tile at interior spaces adjacent exterior
walls where transition of suspended ceiling occurs at new windows.
1.1.6 Installation of exterior insulation and finish system (EIFS) on
existing metal exterior walls of hangar no. 4 The magnitude of
construction is between $500,000.00 AND $1,000,000.00. solicitation
will be issued on or about 28 Jul 97 with a bid opening date of on or
about 27 Aug 97. This bidsolicitation is unrestricted. The applicable
Standard Industrial Classification (SIC) is 1542 with an average annual
gross revenue of $17.0 million for the last three (3) fiscal years.
There is a $43.00 non-refundable charge for each bid package. Payment
in the form of a company check, certified cashier's check or U.S.
postal money order made payable to the Department of the Air Force must
accompany each request. Personal checks or cash will not be accepted.
Only written requests for proposal packages will be honored. No
telephone or telefax requests for proposal packages will be accepted.
NOTICE TO OFFERORS: FUNDS ARE NOT PRESENTLY AVAILABLE FOR THIS PROJECT.
NO AWARD WILL BE MADE UNDER THIS SOLICITATION UNTIL FUNDS ARE
AVAILABLE. THE GOVERNMENT RESERVES THE RIGHT TO CANCEL THIS
SOLICITATION EITHER BEFORE OR AFTER THE OPENING/CLOSING DATE. (0190) Loren Data Corp. http://www.ld.com (SYN# 0186 19970714\Z-0008.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|