COMMERCE BUSINESS DAILY ISSUE OF MAY 22,1997 PSA#1851DA, Tulsa District, Corps of Engineers, PO Box 61, Tulsa, OK
74121-0061 Y -- COOLEY CREEK CHANNEL AND DETENTION SITES, PHASE II, MINGO CREEK,
TULSA, OKLAHOMA SOL DACW56-97-B-0026 DUE 071597 POC Diane Cianci,
Contracting Division, 918-669-7270 This work consists of construction
of channel improvements on the Cooley Creek tributaries portion of the
Mingo Creek watershed in Tulsa, OK. The work includes clearing and
grubbing, common excavation, rock excavation, riprap placement, 1515 LF
of combination concrete lined and grasslined channel with subdrain
system, 1450 LF of concrete U-channel with subdrain system, two grouted
native stone concrete weirs, construction of four new bridges, fencing,
multiple drop inlet structures with interrelated concrete flumes,
sodding, and water and sewer line relocation work. Estimated cost range
of this project is $1,000,000 to $5,000,000. An advanced non-refundable
fee of $62.00 (reduced size) or $123.00 (full size) is required for
each set of specifications. Make check payable to F&A Officer, USAED,
Tulsa, and mail to the attention of Contracting Division. Payment must
be received prior to issuance of plans and specifications. Plans and
specifications will be available on or about 10 June 1997. No phone
calls to order please. All orders will be mailed via first class mail.
Requests for special handling (Fed-X, etc.) will not be honored.