COMMERCE BUSINESS DAILY ISSUE OF MAY 8,1997 PSA#1841USDI, Bureau of Land Management, Oregon State Office (952), P. O. Box
2965, Portland, Oregon 97208-2965 Y -- ROCK CREEK ROAD REALIGNMENT SOL 1422H952-B97-3032 DUE 062797 POC
Sherry Marshall, 503-952-6218 E-MAIL: BLM, or952mb@or.blm.gov. The
work consists of realignment of 10+60 stations of roadway and removal
of existing old subgrade. Work includes clearing and grubbing,
excavating, compacting, and hauling excess excavated material,
installing culverts, constructing subdrain, applying hard rock, asphalt
and turf establishment . Project site is located in Douglas County,
Swiftwater Resource Area, Roseburg District, Oregon. Project range is
between $100,000 and $250,000. Estimated start work is July 15, 1997
and performance time is 60 calendar days. Bonds are required -- Bid
Bond: 20%; Performance Bond: 100%; and Payment Bond: 50%. All
responsible sources may submit an offer which will be considered.
(0125) Loren Data Corp. http://www.ld.com (SYN# 0102 19970508\Y-0002.SOL)
Y - Construction of Structures and Facilities Index Page
|
|