COMMERCE BUSINESS DAILY ISSUE OF JANUARY 21,1997 PSA#1765Arnold Engineering Development Center, ATTN: PKP, 100 Kindel Drive,
Suite A332, Arnold AFB TN 37389-1332 61 -- REPLACE ETF UNIT SUBSTATION #3 SOL F40650997-B-0013 DUE 030397
POC Kimberly Williams, Contract Specialist, (615) 454-7841 This
requirement is for the design, manufacture, assembly, and delivery of
a 1,500/2,000 kilovolt-ampere (kVA), 13.8-kilovolt (kV) to 480-volt (V)
secondary unit substation to replace an existing 36-year-old unit
substation. Delivery shall be FOB Arnold Air Force Base, TN and is
required within 8 months after contract award. Firms responding to this
synopsis should do so in writing and indicate whether or not they are
a small or small disadvantaged business concern. (0015) Loren Data Corp. http://www.ld.com (SYN# 0256 19970121\61-0001.SOL)
61 - Electric Wire and Power and Distribution Equipment Index Page
|
|