COMMERCE BUSINESS DAILY ISSUE OF APRIL 11,1996 PSA#1571Officer in Charge of NAVFAC Contracts; P.O. Box 54306; NSA Memphis;
Millington, TN 38054-0306 R -- A-E ELECTRICAL/MECHANICAL ENGINEERING SERVICES, NAVAL SUPPORT
ACTIVITY MEMPHIS, MILLINGTON, TN Sol N62467-96-D-5212 due 052396.
Contact, Dolores Quinton, (901-873-5061), Contracting Officer, Gary
Busby, (901-873-5061). The work under this contract will generally
include electrical/mechanical studies, preparation of plans,
specifications and cost estimates for predominantly
electrical/mechanical engineering work with some work required from
other disciplines such as, structural, architectural, and civil
engineering disciplines. Electrical work will involve electrical load
flow analysis, primary and secondary electrical repair and construction
project designs, lightning protection systems design, and repair
project designs involving 400 HZ distribution and generation systems.
Mechanical work will involve the design of building HVAC systems for
new and existing facilities, plumbing and piping design, energy
consumption surveys, energy conservation studies and designs as well as
steam, water, and sewage utility system studies and designs. The A/E
shall have in-house capability to field check all existing utilities
and provide AutoCad generated drawings of each of the electrical and
mechanical utilities as layers of station provided, AutoCad generated,
general development map(s). (ACAD/AutoCad as used above shall be that
product distributed by AutoDesk, Inc.). Products in Section 8 of the
SF 255 should not be slanted toward the above work but should be
similar to that mentioned in selection Criteria #2. Asbestos
assessments may be required to determine the presence of asbestos. When
asbestos is present, comprehensive asbestos surveys will be required
which will include sampling and testing, preparing plans and
specifications showing location of the asbestos, and specifying the
procedure to be followed during construction and/or demolition to
prevent the release of airborne asbestos. Firms unable to accept work
which involves asbestos need not apply. Review of contractor
submittals, field inspection during construction, and preparation of
as-builts may be required. The contract shall guarantee a minimum fee
of $10,000 payable in the event the contractor is not required to
perform work under this contract equal to or greater than that amount.
This contract will include an option for a one year extension and the
total fee will not exceed $200,000 per year. No one delivery order
will exceed $99,000. The following criteria for selection, listed in
descending order of importance, will be used. 1. Qualifications:
Technical competence of individual design team members for performing
predominately electrical and mechanical studies and designs. A lesser
consideration will be given to support disciplines of Architectural,
Structural, and Civil to accomplish potential support work. 2.
Experience: Recent experience of the individuals assigned to the
electrical and mechanical engineering groups in: a) performing
technical studies and designs of predominantly electrical and
mechanical projects; b) designing projects IAW Navy criteria; c)
performing interdisciplinary design coordination/reviews; d) using cost
control procedures for design projects where cost is a factor; and e)
post construction contract award services to insure design and
construction quality. 3. Capacity: a) professional ability to perform
multiple projects concurrently and present volume of work and prior DoD
awards. 4. Performance: past performance/ratings on DoD contracts. 5.
Location: a) geographic location of the firm with respect to NAVSUPPACT
Memphis. If the firm has branch offices in more than one city, indicate
the number of personnel in each discipline in the office that will be
responsible for work under this contract; b) knowledge of probable site
conditions that may arise in various locations; c) knowledge of
regulatory requirements that would affect the projects, including
wetlands mitigation; and d) the ability to provide timely professional
responses to issues that could arise during design or construction.
Firms that meet the requirements described in this announcement are
invited to submit completed SF 254 (unless already on file) and SF 255,
U.S. Government Architect/Engineer Qualification Forms, to the office
shown above. In the case where an insufficient number of SF 255's are
received, then firms having a current SF 254 with this office may be
requested to submit a SF 255. This is not a request for proposal (RFP).
(096) Loren Data Corp. http://www.ld.com (SYN# 0076 19960410\R-0011.SOL)
R - Professional, Administrative and Management Support Services Index Page
|
|