COMMERCE BUSINESS DAILY ISSUE OF MARCH 27,1996 PSA#1560Arnold Engineering Development Center, ATTN: PKP, 100 Kindel Drive,
Suite A332, Arnold AFB TN 37389-1332 46 -- AIR STRIPPERS SOL F40650-96-R-0011 DUE 041296 POC Tony
Clayborne, Contracting Officer, (615)454-7841 This requirement is for
two 100 GPM air strippers, two 200 GPM air strippers, one each control
panel for the four air strippers, one level control for the two 100
GPM air strippers, and one 500 GPM liquid phase carbon absorption unit.
The performance period will be 60 calendar days after contractor
receipt of notification of contract award. Any responsible source may
submit a bid which shall be considered. Firms responding to this
synopsis should do so in writing and indicate whether they are a
minority business concern. Foreign participation is authorized. (0085) Loren Data Corp. http://www.ld.com (SYN# 0184 19960326\46-0001.SOL)
46 - Water Purification and Sewage Treatment Equipment Index Page
|
|