COMMERCE BUSINESS DAILY ISSUE OF MARCH 20,1996 PSA#1555U.S. Property & Fiscal Office, Camp Lincoln, 1301 N MacArthur Blvd,
Springfield, Illinois 62702-2399 C -- A&E CONTRACT TO DESIGN THE AIRCRAFT PARKING APRON, POWER CHECK
PAD, AND JET FUEL STORAGE COMPLEX FOR RELOCATION OF 126TH AIR REFUELING
WING FROM O'HARE, IL TO SCOTT AIR FORCE BASE, BELLEVILLE, IL Contact
Point, Brian S. Creech, Contract Specialist, (217) 785-3682. The United
States Property and Fiscal Office for Illinois proposes to enter into
a firm fixed price Architect/Engineer contract to provide Type A, B
design and a option for C inspection services for the design of the
facilities listed above for the 126th Air Refueling Wing from Chicago
to Scott Air Force Base. The types of facilities and approximate square
footage of the facilities are as follows: Jet Fuel Storage Complex
10,000 BBL; Aircraft Parking Apron 82,300 sq. yards; Power Check Pad.
Firms desiring consideration are invited to submit both SF 254 and SF
255 no later than 30 days after publication of this announcement to
USPFO-IL-P&C, ATTN: Brian S. Creech, 1301 N. MacArthur Blvd., Camp
Lincoln, Springfield, Illinois 62702-2399. When submitting the SF 254
and 255, include the number and dollar value of Architect/Engineer
contracts awarded by DoD agencies during the previous twelve (12)
months. Type A (Investigative Services) - Accomplish field surveys and
investigations which may include soil investigations, topographic
surveys; analysis of existing facilities and utilities; study of
various mechanical, electrical, and structural systems as a basis for
recommended functional and safety designs; perform environmental
assessments as may be required to make proper site selection and to
determine basis of design, and perform other investigations as
necessary to make a complete design. Prepare a conceptual design
submittal, including preliminary site plans, typical cross sections and
narrative description of proposed structural design, mechanical
electrical systems, and economic or other justification for selected
systems. Prepare a cost estimate of the major elements of the project
and confirm if the project can be accomplished within budget, fact
finding investigations, to provide pertinent design data and
information including coordination with users and reviewing authorities
to produce complete designs Type B (Pre-Final and Final Design) -
Prepare detailed Architectural/Engineering design calculations, site
plan, and utility plan, prepare outline specifications, detailed cost
estimate, furnish final design, detailed working drawings and
specifications, final design analysis, final cost estimates, and obtain
any required construction/ environmental permits. Type C (Inspection
Services) - Inspection of construction, review of shop drawings and
material submittals and preparation of asbuilt drawings. Evaluation
criteria in descending order of importance are: (1) Professional
Qualifications necessary for satisfactory completion of required
services, to include experienced program manager, architect, civil
engineer, mechanical engineer, electrical engineer, structural engineer
and related support personnel. (2) Specialized experience and technical
competence in the type of work required. (3) Capacity to accomplish the
work in the required time. (4) Past performance on contracts with
government agencies and private industry in terms of cost control,
quality of work, and compliance with performance schedules. (5)
Location in the general geographical area of Scott Air Force Base and
knowledge of the locality of the project. (6) Volume of work previously
awarded to the firm by the Department of Defense in the past twelve
(12) months. The Government's obligation for award of this contract is
contingent upon the availability of appropriated funds. This
procurement is unrestricted. See Note 24. (075) Loren Data Corp. http://www.ld.com (SYN# 0023 19960319\C-0013.SOL)
C - Architect and Engineering Services - Construction Index Page
|
|