COMMERCE BUSINESS DAILY ISSUE OF JULY 18,1995 PSA#1390Contract Administration Section, Procurement and Right-of-Way
Department, Nagoya Construction Bureau, Japan Highway Public
Corporation, 4-1-1 Sakae, Naka-Ku, Nagoya-Shi 460, Japan Y -- JAPAN: S16 CONSTRUCTION POC Tel 81/52/262-7084 FAX N/A product
data a industry sector code: B detailed product description:
Construction Title: Construction of the yatomi overpass (substructure)
on the second tomei expressway; site: from oaza-kusunoki to oaza-
ueno, yatomi-cho, ama-gun, aichi-ken; summary: this Project involves
civil engineering work of 1,567 meters in length, including
substructure work (14 pillar-type piers; 22 one- tier, two-span,
prestressed reinforced concrete piers; three one-tier, one-span,
prestressed reinforced concrete piers; two inverted T-type abutments);
length, 1567 meters; width: main Highway portion, 14.00 meters X 2;
ramp portion, 7.00 meters X 1; earth work volume, 74,000 cubic meters;
bridges, etc.: Substructure work only: main Highway portion, one site,
1,567 meters; ramp portion, one site, 294 meters; piers: main Highway
portion, 37 sets; ramp portion, two sets; abutments: ramp portion, two
sets; foundation work: steel pipe piles, 0.8 meters in diameter,
66,330 meters in length; steel pipe sheet piles, 0.8 meters in
diameter, 2,820 meters in length; U-type retaining Walls, 215 meters in
length; main Materials to be used: concrete, 35,000 cubic meters;
reinforcing steel, 5,800 tons; prestressing steel, 132,000 kilograms;
steel pipe piles, 66,330 meters; steel pipe sheet piles, 2,820 meters;
Construction period: 960 days. C product specifications/technical
data: N/a (not available). D quantity: N/A. e U.S. dollar value: N/A.
F other information: N/A. response data a response language: Japanese.
B best Way to respond: letter. C from manufacturers only: N/A. D
information desired from U.S. firm: N/A. e primary buying factor: the
lowest bid within the estimated price range. F other information:
pre-screening is required to be eligible for bidding. Pre-screening
deadline: 16:00 pm, jul 21, 1995. Bid documents must be obtained
directly from the procuring agency, not from U.S. Embassy. Payment in
yen. A issuing agency: Nagoya Construction Bureau (Japan Highway Public
Corporation) B financing agency: same as above. C price of bid
documents: N/A. D purchase bid documents by: 16:00 pm, jul. 21, 1995.
E tender number required in all Communications: N/A. F performance
bonds required: not required. G closed Procurement procedure: no. H
bidding procedures: open competitive tender. I bid deadline: 13:30 pm,
aug. 31, 1995. J other information: '' kensetsu kogyo shimbun'':
7/11/95. Eligible tender participants: firms qualified to participate
in bidding for this Project must meet all of the following criteria and
have their qualification for this Project screened and confirmed by the
Director of the Nagoya Construction Bureau: 1) firms that Do not fall
under article 4 of the Contract regulations of the Japan Highway Public
Corporation; 2) consortia comprised of two pre- qualified firms having
a score of at least 1,500 points in civil engineering work; 3) firms
that have -- since 1985 (in the past 10 years), as the main contractor
-- actually constructed a pier of at least 10 meters in height. Note:
only Construction projects in which bidders have had a 20 percent or
greater share of involvement are eligible for consideration; 4) firms
that can assign, to the Construction site, a field representative or a
full-time chief engineer or engineering supervisor who has constructed
a pier since 1985 (in the past 10 years), as field representative or
full-time chief engineer or engineering supervisor; 5) firms not
suspended from designation in no. 4 zone by the Japan Highway Public
Corporation; 6) every consortium member firm must meet the following
criteria: a) has been in operation for at least five years in qualified
business under the Construction business law; B) can assign -- to the
Construction site, on a full-time basis -- an engineering supervisor
qualified for this Project under the Construction business law or a
nationally-licensed chief engineer; and C) has an at least 30 percent
share of involvement, and the representative firm must have the
greatest share. Firms pre-screened by the Construction minister
regarding items (a) and (B) in evaluation of their management
operations are exempted from these criteria; and 7) firms not related
by capital or personnel to the contractors involved in this Project.
Post remarks Post contact/prepared by haomori approved by cdukelow
Please send a copy of your response to: Commercial Officer (FCS TOP),
American Embassy, Tokyo, Unit 45004, APO Ap 96337, Refer to TC457.
Please note: All correspondence with the Awarding Authority and/or the
Procuring Agency MUST be in Japanese.. (0195) Loren Data Corp. http://www.ld.com (SYN# 0142 19950717\Y-0004.SOL)
Y - Construction of Structures and Facilities Index Page
|
|