COMMERCE BUSINESS DAILY ISSUE OF JULY 18,1995 PSA#1390Contract Administration Section, Procurement and Right-of-Way
Department, Nagoya Construction Bureau, Japan Highway Public
Corporation, 4-1-1 Sakae, Naka-Ku, Nagoya-Shi 460, Japan Y -- JAPAN: S16 CONSTRUCTION POC Tel 81/52/262-7084 FAX N/A product
data a industry sector code: B detailed product description:
Construction Title: Construction of the nawa overpass West Section
(steel superstructure) on the second tomei expressway; site: from
hiramatsu to mukaihazama, nawa-machi, tokai-Shi, aichi-ken; summary:
this Project involves Construction of 3,560-ton steel superstructure
with prestressed concrete surface for the main Highway bridge (one
site, 610.0 meters); total length: main Highway bridge: one site, 610.0
meters; width: main Highway bridge, 14.00 meters X 2; type of bridge:
11-span continuous, three main steel-plate girders; steel weight, 3,560
tons; main Materials to be used: concrete, 6,400 cubic meters;
reinforcing steel, 1,480 tons; prestressing steel, 170 tons; steel,
3,560 tons; Construction period: 810 days. C product
specifications/technical data: N/a (not available). D quantity: N/A. e
U.S. dollar value: N/A. F other information: N/A. response data a
response language: Japanese. B best Way to respond: letter. C from
manufacturers only: N/ A. D information desired from U.S. firm: N/A. e
primary buying factor: the lowest bid within the estimated price
range. F other information: pre-screening is required to be eligible
for bidding. Pre-screening deadline: 16:00 pm, aug. 18, 1995. Bid
documents must be obtained directly from the procuring agency, not from
U.S. Embassy. Payment in yen. A issuing agency: Nagoya Construction
Bureau (Japan Highway Public Corporation) B financing agency: same as
above. C price of bid documents: N/A. D purchase bid documents by:
16:00 pm, aug. 18, 1995. E tender number required in all
Communications: N/A. F performance bonds required: not required. G
closed Procurement procedure: no. H bidding procedures: open
competitive tender. I bid deadline: 15:00 pm, sep. 29, 1995. J other
information: '' kensetsu kogyo shimbun'': 7/11/95. Eligible tender
participants: firms qualified to participate in bidding for this
Project must meet all of the following criteria and have their
qualification for this Project screened and confirmed by the Director
of the Nagoya Construction Bureau: 1) firms that Do not fall under
article 4 of the Contract regulations of the Japan Highway Public
Corporation; 2) consortia comprised of two pre- qualified firms having
a score of at least 1,200 points in steel superstructure work and one
pre-qualified firm having a score of at least 1,250 points in
prestressed concrete superstructure work; firm to be engaged in steel
superstructure work must not be the same as one to be engaged in
prestressed concrete work; 3) firms that have -- since 1985 (in the
past 10 years), as the main contractor -- actually carried out the
following work: a) in the case of member firm in steel superstructure
work, manufacture at factory of a multi-span continuous, steel-plate
girder bridge; B) in the case of member firm in steel superstructure
work, Construction of a bridge, using on-site stud welding of main
steel girders or steel piers of at least 38 millimeters in breadth; C)
(1) all member firms of steel superstructure work must have the same
experience as in item (a); (2) all or either one of the firms of steel
superstructure work must have the same experience as in item (B); D)
in the case of member firm in prestressed concrete superstructure work,
Construction of prestressed concrete superstructure made of at least
five meters in span length perpendicular to the axis of the bridge
surface. Note: only Construction projects in which bidders have had a
20 percent or greater share of involvement are eligible for
consideration; 4) firms that can assign, to the Construction site, a
field representative or a full-time chief engineer or engineering
supervisor who has had experience with the following work, since 1985
(in the past 10 years): a) in the case of field representative during
the on-site Construction period or full-time chief engineer or
engineering supervisor in steel superstructure work, has had experience
with Construction of a bridge, using on-site stud welding of main steel
girders or steel piers; B) in the case of field representative or full-
time chief engineer or engineering supervisor in prestressed concrete
superstructure work, has had experience with Construction of
prestressed concrete-surface superstructure; 5) firms not suspended
from designation in no. 4 zone by the Japan Highway Public Corporation;
6) firms that can present an adequate plan for steel superstructure
work; 7) every consortium member firm must meet the following criteria:
a) has been in operation for at least five years in qualified business
under the Construction business law; B) can assign -- to the
Construction site, on a full-time basis -- an engineering supervisor
qualified for this Project under the Construction business law or a
nationally-licensed chief engineer; and C) has an at least six tenths
of an equally- divided share of involvement, and the representative
firm must have the greatest share. Firms pre-screened by the
Construction minister regarding items (a) and (B) in evaluation of
their management operations are exempted from these criteria; and 8)
firms not related by capital or personnel to the contractors involved
in this Project. Post remarks Post contact/prepared by haomori approved
by cdukelow Please send a copy of your response to: Commercial Officer
(FCS TOP), American Embassy, Tokyo, Unit 45004, APO Ap 96337, Refer to
TC459. Please note: All correspondence with the Awarding Authority
and/or the Procuring Agency MUST be in Japanese.. (0195) Loren Data Corp. http://www.ld.com (SYN# 0141 19950717\Y-0003.SOL)
Y - Construction of Structures and Facilities Index Page
|
|