COMMERCE BUSINESS DAILY ISSUE OF JULY 7,1995 PSA#1383Department of the Army, Baltimore District, Corps of Engineers, P.O.
Box 1715, Baltimore, MD 21203-1715 Y -- ECS-24 UST AND OIL WATER SEPARATOR UPGRADES, FORT INDIANTOWN GAP,
ANNVILLE, PA SOL DACA31-95-B-0111 DUE 082295 POC Carol Williams or
Marie Johnson (410) 962-5638 or 3464 ECS-24 UST AND OIL WATER SEPARATOR
UPGRADES, FORT INDIANTOWN GAP, ANNVILLE, PA. Est cost is between
$100,000 and $250,000. Completion no later than 210 calendar days.
Construction consists of removing two 5,000 gallon underground storage
tanks (USTs) and replacing them with one 5,000 gallon UST that meets
all regulatory requirements to include spill and overflow protection,
and a leak detection system. Upgrade one existing oil water separator
(OWS) by installing an oil skimming device and replace an existing OWS
with a new one. Full size plans and specs (8) $24.00 p/set; half size
plans and specs (8) $17.75 p/set. Non-Refundable. Make company check
or money order payable to FAO, USAED - Baltimore. (NO CASH ACCEPTED).
Issuance o/a 21 July 1995. Note: The proposed contract is being
considered for 100 percent set-aside for small disadvantaged business
(SDB) concerns. Standard Industrial Code 1629, size standard is $17
million. Interested SDB concerns should, as early as possible, but not
later than 15 days of this notice, indicate interest in the
acquisition by providing to the contracting office above evidence of
capability to perform and a positive statement of eligibility as a
small socially and economically disadvantaged business concern. Proof
of bonding is required. If adequate interest is not received from SDB
concerns, the solicitation will be issued as unrestricted. AMENDMENT
WILL FOLLOW. Therefore replies to this notice are requested from all
types of businesses, as well as from SDB concerns. (0186) Loren Data Corp. http://www.ld.com (SYN# 0141 19950706\Y-0013.SOL)
Y - Construction of Structures and Facilities Index Page
|
|