COMMERCE BUSINESS DAILY ISSUE OF JULY 3,1995 PSA#1380DA, Tulsa District, Corps of Engineers, POB 61, Tulsa, OK 74121-0061 Z -- ALTER CHEMICAL CLEANING ROOM, BUILDING 1055, TINKER AFB, OK SOL
DACA56-95-B-0052 DUE 082295 POC Chief, Contracting Division,
918/669-7275. Work Consist of: Construct a temporary chemical cleaning
process and relocate existing process equipment including installation
of temporary piping, electrical and exhaust systems. Demolish existing
cleaning area including removal of ceiling and mech/elec systems as
required. Demolition will include removal of asbestos containing floor
tile. Construct a new Class 300,000 chemical cleaning facility
including new metal stud walls, gypsum board ceiling, air lock
vestibule, environmental control system, process exhaust system,
process piping, and electrical power/lighting systems. Also included
will be the construction of new mechanical room, reinstallment of
existing process equipment, balancing, testing and commissioning of new
mech/elec systems, and the removal of all temporary facilities.
Estimated cost range of this project if from $100,000 to $250,000. Cost
for plans and specifications are $17.00 (half-size) and $25.00
(full-size). Make check payable to the F&A Officer, USAED Tulsa, marked
for the attention of the Contracting Division. No phone calls to order
please. All orders will be mailed via first class mail. Request for
special handling (Federal Express, Overnight Express, etc.) will not be
honored. See Note 4. (0180) Loren Data Corp. http://www.ld.com (SYN# 0181 19950630\Z-0040.SOL)