COMMERCE BUSINESS DAILY ISSUE OF june 20,1995 PSA#1371Operational Contracting Office, 1538 Atlantic Ave, Dobbins ARB, GA
30069-4824 Z -- PRE-SOLICITATION NOTICE Sol F09609-95-B-0005. Due 080795. Contact
Point, Kevin R. Brooks, 404/919-4987/ Charlotte A. Delli, 404/919-4981,
Contracting Officer. Projects FGWB 92-0054. Repair Airfield Lighting
and FGWB 92-0068. Repair and Alter Airfield Lighting Controls at
Dobbins ARB, Ga. The appropriate SIC code for size standard is 1731.
Work includes, but is not limited to: repair of all elements of the
airfield lighting system to include the testing and replacement of all
defective conduits, cables, fixtures, light bases, lamps isolation
transformers, power transformers, regulators, junction boxes,
regulators, junction boxes, cutouts, switches, control cables, and all
associated airfield circuit and lighting equipment; replace the Visual
Approach Sight Indicator system (VASI) with a Precision Approach Path
Indicator light system (PAPI); replace west end overrun approach
fixtures, defective semi flush light fixtures and isolation
transformers; replace isolation transformers; install new control
system to control all facets of the airfield lighting system; provide
and install new control system and necessary switching equipment to
control all functions of the central air field lighting vault
regulators, west end vault regulators, beacon tower pole transformer
and all associated airfield lighting circuits. The contractor or
sub-contractor performing work on the airfield lighting and lighting
control projects must have successfully completed at least two projects
similar in nature involving installation of runway and taxiway lighting
at an active air carrier airport or military airfield and the
installation of airfield lighting control systems (computerized type
and traditional relay type) valued over $500,000 in the five
consecutive years immediately preceding bid opening date. The estimated
cost is between $1,000,000 and $5,000,000. The period of performance
will be 270 days. This procurement is being considered as a potential
100% set-aside for small, disadvantaged business (SDB). Within 15 days
of this notice, any interested SDB should provide written notice to
the Contracting Officer stating that it positively intends to bid on
the project and is capable and qualified to perform the work described.
If sufficient interest is not received from SDB concerns, the
procurement will be full and open competition. Therefore, all
interested firms should respond to this notice. The soicitation will be
issued on or about 06 Jul 95 with bid opening date on or about 07 Aug
95. Only written responses for solicitations will be honored. No
telephone or telefax requests will be accepted. Your written request
should make reference to ``F09609-95-B-0005'' and include your company
name, address, phone number, and point of contact. (166) Loren Data Corp. http://www.ld.com (SYN# 0178 19950619\Z-0009.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|