COMMERCE BUSINESS DAILY ISSUE OF may 25,1995 PSA#1354DIRECTORATE OF CONTRACTING, ANNISTON ARMY DEPOT, 7 FRANKFORD AVE,
ANNISTON AL 36201-4199 46 -- FURNISH AND INSTALL ULTRAVIOLET DISINFECTION SYSTEM (UVS) SOL
DAAC01-95-R-0021 DUE 062195 POC Contract Specialist, Valerie D. Jones,
(205)235-7748, Contracting Officer, R. S. Corrigan, (205)235-6231 The
acquisition requires the furnishing and installing of an Ultraviolet
Disinfection System (UVS) to be used at the Sewage Treatment Plant at
Anniston Army Depot for final effluent treatment. The UVS will replace
the current chlorination process. The system must fit within an open
grass area of 10' Width X 25' Long. Contractor shall be responsible for
all concrete work (concrete pad), plumbing, etc. System must connect to
existing piping. System shall be designed to treat an average daily
flow of 620,000 gallons per day and a peak flow of 800,000 gallons per
day. UVS shall be designed/installed to allow gravity flow into
channel. UVS shall be designed to adequately treat effluent with a
maximum exposure time of 6-10 seconds to achieve reduction in micro
organisms below these requirements: Effluent Characterisitics (Fecal
Coliform-FEC) and Discharge Limitations (Daily Maximum and Number
colonies per 100 ml sample (50)). The delivery time is within 90 days
after contract award date. All responsible firms may submit a bid which
we shall consider. Please request your solicitation in writing,
telephone requests will not be accepted. You may request a copy of the
solicitation by faxing your request to (205)235-6353.(0143) Loren Data Corp. http://www.ld.com (SYN# 0300 19950524\46-0001.SOL)
46 - Water Purification and Sewage Treatment Equipment Index Page
|
|