COMMERCE BUSINESS DAILY ISSUE OF APRIL 17, 1995 PSA#1326University of California, Lawrence Livermore National Laboratory, P. O.
Box 5502, Livermore, CA 94551 C -- ARCHITECT ENGINEER DESIGN SERVICES FOR THE LASER AND TARGET AREA
BUILDING FOR THE NATIONAL IGNITION FACILITY SOL B265199 DUE 051195 POC
Subcontract Administrator: Ms. Gennie McPeak, (510) 423-8454 The
University of California, Lawrence Livermore National Laboratory
(LLNL), operating under Prime Contract W-7405-ENG. 48 with the U. S.
Department of Energy (DOE), intends to subcontract for
Architect-Engineering (A-E) Design Services that includes Advanced
Conceptual Design, Title I Design Services, with an option for Title II
Design Services and Title III Construction Support Services for the
National Ignition Facility (NIF) Laser and Target Area Building (LTAB).
The National Ignition Facility project team has completed a Conceptual
Design. The DOE has designated LLNL at Livermore, California, as the
preferred site for the NIF. However, final site selection will be made
by the DOE and validated through the National Environmental Policy Act
(NEPA) process. Livermore is located approximately 50 miles southeast
of San Francisco, California. Alternate sites being considered are
Sandia National Laboratory in Albuquerque, New Mexico, Los Alamos
National Laboratory in Los Alamos, New Mexico, and the Nevada Test Site
approximately 60 miles north of Las Vegas, Nevada. Selection will be
limited to Architect-Engineering Firms/Joint Venture firms located in
the continental United States and employing a minimum combined
full-time staff of 200 employees, representing capabilities of
disciplines as follows: Architectural, Civil Engineering, Electrical
Engineering, Estimating, Mechanical Engineering, Structural
Engineering, Vibration Isolation of Large Structures, Precise Thermal
Control of Large Open Buildings, Integrated Facility Design with
Complex Experimental Equipment, and Value Engineering. Aggregation of
disciplinary capabilities is allowed if affiliations are through joint
ventures, partnerships, consultant agreements, corporate structure, or
other formal subcontracting agreements. Lead Architects and Engineers
within the disciplines assigned to the project shall have professional
registration. HOW TO OBTAIN A PROJECT NOTICE: Release of the project
notice is contingent upon receipt of appropriate DOE solicitation
approvals. The project notice will be available on or about April 7,
1995 and may be obtained by contacting the LLNL Contracting and
Materiel Management Department, AE/Construction Group, (510) 422-7981
or (510) 423-8454 between the hours of 9:00 a.m. and 3:00 p.m. (PST).
Firms who meet the qualification requirements described in the Project
Notice and who wish to be considered will be required to submit eight
(8) copies of Standard Forms 254 and 255 with appropriate supplemental
data by 3:00 P.M. ON MAY 11, 1995 . Questions regarding this Notice may
be addressed to Gennie McPeak at (510) 423-8454. (0103) Loren Data Corp. http://www.ld.com (SYN# 0032 19950414\C-0005.SOL)
C - Architect and Engineering Services - Construction Index Page
|
|