COMMERCE BUSINESS DAILY ISSUE OF APRIL 10,1995 PSA#1321Contract Administration Section, Procurement and Right-of-Way
Department, Sapporo Construction Bureau, Japan Highway Public
Corporation, Kita 4, Nishi 5-1-3, Chuo-Ku, Sapporo-Shi 060, Japan 99 -- JAPAN: POC Tel 81/11/242-2168 FAX N/A S16 Construction product
data a industry sector code: B detailed product description:
Construction Title: Construction of the osatsu Section on the
trans-hokkaido expressway; site: osatsu and kyowa, chitose-Shi,
hokkaido; summary: this project involves Construction of a tentatively
two-lane Highway of 3, 359 meters length, including cutting and
filling of 678 cubic meters of earth and substructure work for a bridge
at three sites for 97 meters; total length: 3,359 meters; width: 12.0
meters for the Highway portion, 10.0 and 10.5 meters for the bridge
portion; earth work volume: 678,000 cubic meters; bridge, etc.:
Substructure work only at three sites for 97 meters, five sets of
abutments, one set of pier; cross structures: culvert boxes at 10
sites, culvert rim at one site, culvert pipe at one site; main
materials to be used: 21,600 cubic meters of concrete, 1,716 tons of
reinforcing steel; Construction period: 1,200 days (winter recess: nov.
16 to apr. 15). C product specifications/technical data: N/a D
quantity: N/a e U.S. dollar value: N/a F other information: N/a
response data a response language: Japanese. B best Way to respond:
letter. C from manufacturers only: N/a D information desired from U.S.
firm: N/a e primary buying factor: the lowest bid within the estimated
price range. F other information: pre-screening required to be eligible
for bidding. Pre-screening deadline: 16:00 pm, apr. 17, 1995. Bid
documents must be obtained directly from the submitting agency, not
from U.S. Embassy. Payment in yen. A issuing agency: Sapporo
Construction Bureau, Japan Highway Public Corporation B financing
agency: N/a C price of bid documents: N/a D purchase bid documents by:
16:00 pm, apr. 17, 1995. E tender number required in all
communications: N/a F performance bonds required: not required. G
closed Procurement procedure: N/a H bidding procedures: open
competitive tendering. I bid deadline: 14:00 pm, May 31, 1995. J other
information: ''kensetsu kogyo shimbun'': 4/5/95. Eligible tender
participants: firms qualified to participate in bidding for this
project must meet all of the following criteria and have their
qualifications for this project screened and confirmed by the director
of the Sapporo Construction Bureau: 1) firms that do not fall under
article 4 of the Contract regulations of Japan Highway Public
Corporation; 2) firms pre-qualified for open competitive tendering on
road and earth work by the Sapporo Construction Bureau for fy 93/94, or
consortia comprised of two qualified firms; 3) firms that have -- in
the past five years (since 1990) as the main contractor -- actually
carried out Construction of a Highway of at least one kilometer length,
involving at least 200,000 cubic meters of earth work volume. Note:
only Construction projects in which bidder has had a 30 percent or
greater share are eligible for review, and in the case of consortium,
all member firms must have a similar experience; 4) firms that can
assign to the Construction site a field representative and a full-time
chief engineer or engineering supervisor who meet the following
criteria: have had experience with road and earth work of at least one
kilometer length as field representative or as chief engineer or
engineering supervisor in the past five years (since 1990); 5) firms
not suspended from designation in no. 1 zone by the Japan Highway
Public Corporation; 6) in the case of consortium, every consortium
member firm must meet the following criteria: a) has been in operation
for at least five years in qualified business under the Construction
business law; B) can assign to the Construction site on a full-time
basis an engineering supervisor qualified for this project under the
Construction business law or a nationally-licensed chief engineer; and
C) has a 30 percent or greater share of involvement, and the
representative firm must have the greatest share. Firms pre-screened by
the Construction minister regarding items (a) and (B) in evaluation of
their management operations are exempted from these criteria; and 7)
firms not related by capital or personnel to the contractors involved
in this project. Post remarks Post contact/prepared by haomori approved
by gtaevs Please send a copy of your response to: Commercial Officer
(FCS TOP), American Embassy, Tokyo, Unit 45004, APO Ap 96337, Refer to
TC339.. (0096) Loren Data Corp. http://www.ld.com (SYN# 0254 19950407\99-0002.SOL)