COMMERCE BUSINESS DAILY ISSUE OF FEBRUARY 13,1995 PSA#1282Contract Division, Toru Nakamura, Director-General, New Tokyo
International Airport Authority, Itopia Nihombashi Honcho Building,
2-7-1 Nihombashi Honcho, Chuo-Ku, Tokyo 103 99 -- JAPAN: SOL KENSETSU KOGYO SHIMBUN: 02/07/95 PG. 3. DUE 110095
POC Tel 81/3/3639-6285 S1542 reconstruction of passenger terminal
opening time and date 11:00, mar. 29, 1995 open 1) Construction Title
reconstruction of North wing of new Tokyo International passenger
terminal one (phase one); 2) Construction site inside of new Tokyo
International Airport, narita-Shi, chiba-Ken; 3) work summary a) number
of Floor and size of structure: 5 stories with a basement, 62,000
square meters in total Floor area; B) structure made of steel frame; C)
work involved earth work, piling, and underground skeleton work for
passenger terminal facilities; 4) Construction period approx. 25
months; 5) main materials to be used approx. 18,900 cubic meters of
concrete; approx. 2,400 tons of reinforcing steel; 6) deadline for
submission of application forms/related documents for qualification
screening 16:00, feb. 20, 1995; 7) finance Department, new Tokyo
International Airport Authority, 2-7-1 Nihombashi Honcho, Chuo-Ku,
Tokyo submitting Agency, not from U S. Embassy. Date of publication in
''kensetsu kogyo shimbun'' 020795. Post contact/prepared by gloose
Please send a copy of your response to: Commercial Section (FCS TOP),
American Embassy, Tokyo, Unit 45004, APO Ap 96337, Refer to
TC0293..(0040) Loren Data Corp. http://www.ld.com (SYN# 0426 19950210\99-0011.SOL)
99 - Miscellaneous Index Page
|
|