COMMERCE BUSINESS DAILY ISSUE OF JANUARY 30,1995 PSA#1272Jiro Inose, Director-General, Construction Department, Teito Rapid
Transit Authority, 3-19-6 Higashi-Ueno, Taito-Ku, Tokyo 110 99 -- JAPAN: SOL KENSETSU KOGYO SHIMBUN: 01/25/95 PG. 3. DUE 150095
POC Tel 81/3/3837-7110 S1629 Construction of urban Transit tunnel
opening time and date 15:00, mar. 14, 1995. Open 1) Construction Title
first-phase Public works at kawaguchi-minami site on saitama Rapid
Transit line; 2) site 1-3-chisaki motogo, kawaguchi-Shi to 5-3-chisaki
minami, hatogaya-Shi, saitama-ken; 3) summary Construction of an urban
Transit tunnel of 9 50 meters outer diameter and 1,639 001 meters
length by the slurry- pressure shield tunneling method; 4) Construction
period 52 months; 5) main Materials to be used 1,632 meters of lining
plates; 6) deadline for submission of application forms/related
documents for qualification screening feb 6, 1995; 7) contact for
tender documents: administration Division, Construction Department,
Teito Rapid Transit Authority, 3-19-6 Higashi-Ueno, Taito-Ku, Tokyo 110
qualifications for tender participants consortia comprised of two or
three firms that meet the following criteria and that have been
pre-qualified for bidding on this project by the Director of the
Construction Department 1) firms that are solvent; 2) firms that have
been rehabilitated from bankruptcy; 3) firms qualified for Construction
works under article 3 of the Construction business law; 4) firms that
are sound in their business operations; 5) firms that have not
perpetrated any of the following Acts in the past two years from the
deadline for qualification screening a) intentionally carried out poor
work or unfairly cheated on quality/quantity of Materials in a
contract; B) interfered with fair competition, fair pricing or colluded
for unfair benefit; C) interfered with a winner's signing of a contract
or interfered with a contractor from carrying out assigned duties; D)
interfered with official staff's supervising or inspecting a contract;
and e) unjustifiably reneged on carrying out a contract; 6) firms not
employing as representative, Manager, or staff anyone who has
misbehaved per (a) to (e) within two years of their misconduct; 7)
firms grade ''a''-qualified for Public works by this Authority for fy
93/94; 8) firms that have -- since 1985 as the main contractor --
actually carried out Construction of an urban Transit tunnel of at
least 6 0 meters outer diameter, including one under Construction at
this time, by the closed-type, slurry-, earth-, or
slurry/earth-pressure shield tunneling method for this Authority, a
pubic subway, a third-sector Transit, Japan railway Construction Public
corporation, and Japan railway companies note: only Construction
projects in which the bidder has had a 20 percent or greater share are
eligible for review; 9) firms that can assign to the Construction site
a full-time chief engineer or engineering supervisor who meets the
following criteria a) is qualified as a certified first-class
Construction supervisor or a Construction engineer under the engineers
law; B) has since 1985 had similar Construction experience as
described in item (8) above, and similar experience refers to
Construction of an urban Transit tunnel by the closed-type shield
tunneling method; and C) in the case of engineering supervisor, is
qualified to supervise designated Construction works; 10) firms not
currently suspended from designation by this Authority; 11)
requirements for a designated consortium a) comprised of two or three
firms that meet (1) to (7) above, and the same firm cannot belong to
more than one consortium; B) all member firms must have Construction
experience as described in (8) above; C) all member firms must employ
a chief bngineer or engineering supervisor as specified in (9)-(a) to
(C) above, and can assign him or her to the Construction site on a
full-time basis; D) all member firms must have an involvement ratio of
at least 30 percent for two-firm consortium and of at least 20 percent
for thr ee-firm consortium; e) the representative firm of a consortium
must have Construction experience as consortium's representative, and
must have the greatest share of involvement among all members; F) a
consortium is valid from the date of its designation to the date of
completion of this project, and for firms other than the bid winner, to
the date of contract signing for this project; and G) the Title of a
consortium ''aa-bb Construction consortium'' for two-firm consortium,
and ''aa-bb-cc Construction consortium'' for three-firm consortium bid
documents must be obtained directly from the submitting agency, not
from U S. Embassy. Date of publication in ''kensetsu kogyo shimbun''
012595. Post contact/prepared by gtaevs Please send a copy of your
response to: Commercial Section (FCS TOP), American Embassy, Tokyo,
Unit 45004, APO Ap 96337, Refer to TC0282.. (0026) Loren Data Corp. http://www.ld.com (SYN# 0305 19950127\99-0002.SOL)