COMMERCE BUSINESS DAILY ISSUE OF JANUARY 18,1995 PSA#1264Daisuke Takahashi, Director-General, Shizuoka Construction Bureau,
Japan Highway Public, Corporation, 11-30 Miyuki-Cho, Shizuoka-Shi,
Shizuoka-Ken 420 99 -- JAPAN: SOL KENSETSU KOGYO SHIMBUN: 01/10/95 PG. 3. DUE 110095
POC Tel 81/54/272-4881 S1611 Construction of Expressway opening time
and date 11:00, mar. 28, 1995. Open 1) Construction Title first-phase
Construction of the third shimizu tunnel on the second Tokai
Expressway; 2) site oaza-yoshihara, shimizu-Shi, Shizuoka-Ken; 3)
8UMMARY this project is to construct an approx. 230- meter Highway,
mainly involving a three-lane-Section tunnel (earth work volume 450,000
cubic meters) work involves approx 200 meters tunneling on the ''up''
route and approx 50 meters tunneling on the ''down'' route in the main
tunnel of the third shimizu tunnel; approx 1,700 meters excavation of
a pilot tunnel, using the tunnel-boring machine in both routes and the
communication pilot tunnel; approx 180 meters earth work; extension
(the ''down'' route extension) 227 meters; width - Highway portion 11
75 meters X 2, tunnel portion 0 meters X 2; earth work volume 450,000
cubic meters; tunnel 250 meters; and cross structure - precast concrete
arch culvert at one site; 4) Construction period 750 days; 5) main
materials to be used approx. 8,000 cubic meters of concrete, approx
9,000 square meters of concrete spraying, approx 600 tons of steel
beams (support), approx. 400 tons of reinforcing steel; 6) documents
for qualification screening 16:00, feb. 9, 1995; 7) contact for Tender
documents General Affairs Department, Shizuoka Construction Bureau,
Japan Highway Public Corporation, 11-30 Miyuki-Cho, Shizuoka-Shi,
Shizuoka-Ken 420 eligible Tender participants firms qualified to
participate in this project's bidding must satisfy all of the following
conditions and have their qualifications for this project's bidding
screened and confirmed by the Director of the Shizuoka Construction
Bureau 1) firms that do not fall under article 4 of the contract
regulations of Japan Highway Public Corporation; 2) consortia comprised
of three firms pre-qualified for open competitive tendering on Public
works by the Tokyo first Construction Bureau of Japan Highway Public
Corporation for fy 93/94; 3) each member firm must have -- in the past
five years (since 1989) as the main contractor -- actually carried out
Construction of a Highway tunnel of at least 1 kilometer extension and
at least 50 square meters designed inner Section by the ''natm''
method at least one member firm must have -- in the past five years
(since 1989) as the main contractor -- actually carried out
Construction of a Highway tunnel of at least 110 square meters designed
inner Section by the ''natm'' method and at least one member firm must
have -- in the past five years (since 1989) as the main contractor --
actually carried out tunneling, using a tunnel-boring machine of at
least 2 meters excavation diameter note: only Construction projects in
which bidder has had a 30 percent or greater share are eligible for
consideration; 4) firms that can as8IGN to the Construction site a
field Representative or a full-time chief engineer or engineering
supervisor who meets the following criteria for the past five years
(since 19G9) as field Representative or as chief engineer or
engineering supervisor, has constructed a tunnel by the '' natm''
method; 5) firms not suspended from designation in no 3 zone by Japan
Highway Public Corporation at deadline dates for qualification
screening and bid opening; 6) firms that can present an adequate plan
for the tunneling work; 7) each member firm must satisfy the following
criteria a) has been in operation for at least five years in qualified
business under the Construction business law; B) can assign to the
Construction site a full-time engineering supervisor qualified for this
project under the Construction business law or a full- time
nationally-licensed chief engineer; and C) has an at leas T 20 percent
share of involvement, and the Representative firm must have the
greatest share firms pre-qualified by the Construction minister
regarding items (a) and (B) in evaluation of their management
operations are exempted from these criteria; and 8) firms not related
by capital or personnel to the contractors involved in this project
(see Tender documents for details) bid documents must be obtained
directly from the submitting agency, not from U S. Embassy. Date of
publication in ''kensetsu kogyo shimbun'' 011095. Post contact/prepared
by gtaevs Please send a copy of your response to: Commercial Section
(FCS TOP), American Embassy, Tokyo, Unit 45004, APO Ap 96337, Refer to
TC0251.. (0013) Loren Data Corp. http://www.ld.com (SYN# 0436 19950117\99-0002.SOL)
99 - Miscellaneous Index Page
|
|