SOLICITATION NOTICE

Y -- 528A6-19-604 Renovate B76 6th floor

Notice Date
4/28/2026 11:50:10 AM
 
Notice Type
Solicitation
 
NAICS
236220 — Commercial and Institutional Building Construction
 
Contracting Office
242-NETWORK CONTRACT OFFICE 02 (36C242) ALBANY NY 12208 USA
 
ZIP Code
12208
 
Solicitation Number
36C24226B0048
 
Response Due
4/30/2026 9:30:00 AM
 
Archive Date
05/30/2026
 
Point of Contact
Devan Bertch, Contract Specialist
 
E-Mail Address
Devan.Bertch@va.gov
(Devan.Bertch@va.gov)
 
Awardee
null
 
Description
RFI Questions and VA Responses 528A6-19-604 Renovate B76 6th floor Solicitation #: 36C24226B0048 RFI 6: DWG M202 Per keynote 5 we are to install steam drip trap. Please indicate what detail is to be used for this note and if this line is intended for future use and capped or is to be tied back into steam condensate system RFI 6 VA Response: Tie it back to steam condensate system. RFI 7: Do we happen to know who has the Speaker/PA system so I can reach out to them for new speakers and such to match the existing system RFI 7 VA Response: Avaya is one supplier that is utilized on station. RFI 8: Regarding the tile to be removed/replaced on the 5th� floor shown on A111: Normally, if the old plaster ceiling above contains Asbestos-Containing Material (ACM), we assume the dust on top of the existing ceiling tiles is also hazardous. Should this be presumed to perform demolition under containment conditions?� RFI 8 VA Response: Yes Containment conditions will need to be provided as and when required by the applicable regulations. RFI 9: The documents show the 6th� floor deck is 75 -9 ¼ , but� we can t confirm that the first floor is 0 -0 datum. Can you provide any additional� details regarding overall� elevations?� RFI 9 VA Response: The documentation shows the 7th floor (attic floor) to be 75 -9 ¼ , sixth floor decking is approximately 65 from first floor RFI 10: Will the VA allow elevator use to move materials to the 6th floor. RFI 10 VA Response: The VA will allow elevator use to move new materials and construction equipment. RFI 11: In regard to drawings ASB-01 - General Note 1 states there is floor tile / mastic removal in rooms 611, 619, 613, 615, 615A, 617, and 623 - however on my prints three rooms are only indicated as work area for tile / mastic abatement. I tried referencing G-102 but the room numbers are not listed.� � RFI 11 VA Response: Please refer to the following ASB-01 representation, RFI 12: On drawings ASB-01 - General Note 15 - states ACM glue is present on ceilings on the 5th� floor - G102 shows that there is work above ceiling on the 5th� floor? Will this area be a part of the abatement scope? There is no mention of removal other than general note 15 - stating that acm is present on the floor. RFI 12 VA Response:� ASB-01 identifies 6th floor abatement areas. General note 15 is a safety awareness note for demolition and reinstall new connections at the riser for plumbing and mechanicals. ACM is present in the corridor ceiling of the fifth floor. Additional abatement to the fifth floor is not required. Please refer to the following ASB-01 representation, RFI 13: Is the subfloor a concrete base or wood?� RFI 13 VA Response: Concrete RFI 14: Is an infra-red heating unit mandatory for floor tile removal? Referencing section 028213 - 19 - 52 section 4.� RFI 14 VA Response: Yes
 
Web Link
SAM.gov Permalink
(https://sam.gov/workspace/contract/opp/f4fb2ead5f02459ca060c9bd158473bf/view)
 
Record
SN07794254-F 20260430/260428230038 (samdaily.us)
 
Source
SAM.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's SAM Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2026, Loren Data Corp.