J -- RFQ Amendment (Questions) 13 MAR 26 Repair Services - Chiller Plant Skid 1 & 2 Pump

Notice Date
3/10/2026 2:50:40 PM
 
Notice Type
Combined Synopsis/Solicitation
 
NAICS
333415 — Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment Manufacturing
 
Contracting Office
256-NETWORK CONTRACT OFFICE 16 (36C256) RIDGELAND MS 39157 USA
 
ZIP Code
39157
 
Solicitation Number
36C25626Q0449
 
Response Due
3/13/2026 8:00:00 AM
 
Archive Date
05/12/2026
 
Point of Contact
Rhonda Gibson, Contract Specialist, Phone: 7132911515
 
E-Mail Address
rhonda.gibson2@va.gov
(rhonda.gibson2@va.gov)
 
Small Business Set-Aside
SDVOSBC Service-Disabled Veteran-Owned Small Business Set Aside
 
Awardee
null
 
Description
Amendment 00001 provides responses to questions for Solicitation Number 36C25626Q0449 and extends the due date of this solicitation. 1. Photos of the pumps/motors showing piping arrangement, electrical connection, and nameplate data. Are VFDs required? Is there any BAS connections or interlocks for the pumping system? ANS: The pics are attached to the email for this project. VFD's are required but not being replaced. No BAS connections needed. 2. Electrical for the Motors: HP, Voltage, Amperage and disconnecting means and locations. ANS: The information are located in the pics attached to the email. Electrical is all on name plate of pumps in pics 3. Pump capacity information: Flow Rate in GPM, & Pumping Head. ANS: The information are located in the pics attached to the email. Flow rate and GPM are on name plates in pics 4. What type of insulation is installed and thickness? ANS: The insulation is wrapped fiberglass insulation 2"" thick 5. Is pump an End Suction, Double Suction, or In Line type Pump. ANS: See pics of pumps for the alignment for inlet and outlet 6. What is the pipe size for the Taco Triple Duty Valves to be installed. ANS: The piping is 12"" for chiller 1 and 10"" for chiller 2 Clarify the questions come from the scope: ""The Contractor shall provide all tools, shipping, delivery, personnel, transportation, demolition, removal of old equipment, installation of new equipment, modifications to existing piping, to deliver and install the necessary equipment for repairing Chillers 1, and 2 ANS: The contractor must install both pump/motor for each chiller 1&2 and triple duty valve for both chillers. 2. The scope is to provide regular system health checks, preventative/routine maintenance, repairs, onsite training, and access to a technical support team in support of two industrial chillers and their subcomponents which consist of, but not limited to: magnetic drive pumps, piping, electrical connections, regulator valves, pneumatic actuators, gauges and indicators, heat exchangers, AC drives, and input modules. "" ANS: The contractor after installation must verify the installation correct with functional for the 2 chillers pump/motors and triple duty valve.
 
Web Link
SAM.gov Permalink
(https://sam.gov/workspace/contract/opp/5972e08511854dc5aa9c71861f985f70/view)
 
Place of Performance
Address: Alexandria, VA Medical Center 2495 Shreveport Hwy, Pineville, 71360
Zip Code: 71360
 
Record
SN07739818-F 20260312/260310230043 (samdaily.us)
 
Source
SAM.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's SAM Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2026, Loren Data Corp.