SOLICITATION NOTICE
Z -- CANAVERAL HARBOR MAINTENANCE DREDGING, BREVARD COUNTY, FLORIDA
- Notice Date
- 12/16/2024 9:24:01 AM
- Notice Type
- Solicitation
- NAICS
- 237990
— Other Heavy and Civil Engineering Construction
- Contracting Office
- W074 ENDIST JACKSNVLLE JACKSONVILLE FL 32207-0019 USA
- ZIP Code
- 32207-0019
- Solicitation Number
- W912EP25B0006
- Response Due
- 12/12/2024 10:00:00 AM
- Archive Date
- 01/31/2025
- Point of Contact
- Timothy Humphrey, Phone: 9042321072, NICOLE BATISTA-CRUZ, Phone: 9042323275
- E-Mail Address
-
TIMOTHY.G.HUMPHREY@USACE.ARMY.MIL, nicole.m.batista-cruz@usace.army.mil
(TIMOTHY.G.HUMPHREY@USACE.ARMY.MIL, nicole.m.batista-cruz@usace.army.mil)
- Awardee
- null
- Description
- This project will consist of maintenance dredging at Canaveral Harbor, FL to remove approximately 1.2 million cubic yards of shoal material at Cut-1A to the West Access Channel (WAC), the Middle Turning Basin (MTB), the South Jetty Sediment Trap (SJST), the Trident Access Channel (TAC), and the Trident Turning Basin (TTB). All material will be disposed of in the designated Ocean Dredged Material Disposal Site (ODMDS). The ODMDS is located 4.0 to 8.0 nautical miles from the designated dredging areas. Project work also includes environmental species monitoring, turbidity monitoring, and stand by time. Project work will be split between Base and one Option as shown on the plans and outlined in the project bid schedule. Only dredges with a current U.S. Coast Guard Certification of Inspection for the intended use of the vessel will be allowed to work seaward of the boundary line under the contract. The Invitation for Bid (IFB) will be issued on or about 12 November 2024 and bids will be due on or about 12 December 2024. NAICS Code 237990, Dredging and Surface Cleanup Activities. The Small Business Standard is $37 million The Magnitude of construction is $10,000,000.00 - $25,000,000.00.This project will have an estimated period of performance of 260 calendar days after issuance of Notice to Proceed (NTP), including 60 calendar days to commence work. The total completion time of 260 calendar days include the following: 240 Calendar days for the BASE (Incl. Commencement and Demob) 20 Calendar Days for OPTION A THIS IS AN UNRESTRICTED REQUIREMENT. NOTE: U.S. COAST GUARD CERTIFIED DREDGE IS REQUIRED TO COMPLETE THE WORK. Solicitation will be issued in electronic format only and will be posted on the Sam.gov website at https://sam.gov/. In order to receive notification of any amendments to this solicitation, interested vendors must REGISTER AS AN INTERESTED VENDOR on the Sam.gov website at https://sam.gov/. If you are not registered, the Government is not responsible with providing you with notification of any amendments to this solicitation. You must be registered in the System for Award Management (SAM) in order to be eligible to receive an award from this solicitation. For additional information, please call 866-606-8220 or visit the SAM website at https://www.sam.gov/.
- Web Link
-
SAM.gov Permalink
(https://sam.gov/opp/a2c029e437a04e598dced7a3a3b880e8/view)
- Record
- SN07292961-F 20241218/241216230107 (samdaily.us)
- Source
-
SAM.gov Link to This Notice
(may not be valid after Archive Date)
| FSG Index | This Issue's Index | Today's SAM Daily Index Page |