H -- COLUMBUS AFB, MS FAC# 141 & 145 FUEL TANK INSPECTION

Notice Date
10/15/2024 12:24:36 PM
 
Notice Type
Combined Synopsis/Solicitation
 
NAICS
541990 — All Other Professional, Scientific, and Technical Services
 
Contracting Office
W071 ENDIST OMAHA OMAHA NE 68102-4901 USA
 
ZIP Code
68102-4901
 
Solicitation Number
W9128F25Q0006
 
Response Due
10/17/2024 2:00:00 PM
 
Archive Date
11/01/2024
 
Point of Contact
Kristal Dobry, Jae Chang
 
E-Mail Address
kristal.d.dobry@usace.army.mil, jae.chang@usace.army.mil
(kristal.d.dobry@usace.army.mil, jae.chang@usace.army.mil)
 
Small Business Set-Aside
SBA Total Small Business Set-Aside (FAR 19.5)
 
Description
Q&A� Question 1 Will the Government have the floating roof legs set prior to the contractor�s arrival? Answer 1 The floating roof legs will be set prior to contractor arrival. Question 2 Under paragraph 4.1.4, the coatings are to be repaired IAW UFGS 09 97 13.27 and 09 97 13.17. Can these repairs be completed by a simple coating contractor without additional inspection or will a SSPC QS1 contractor with a SSPC QP5 inspector be required as listed by the UFGS specifications? Answer 2 The repairs can be made without a QP5 or QS1 permitting the Contractor follows process within the coating specifications. Note that the specification requires a coatings plan to be submitted. Question 3 CLIN 0004, Paragraphs 4.1.2, and 4.1.12, where will the fuel be transferred and what is the approximate distance? Is it preferable to accomplish this via vacuum truck or existing piping and pumps? Answer 3 Base will empty the tank and turn over to the KTR for cleaning.� Attachment B identifies residual fuel. Question 4 Is electricity and water available on site for cleaning crew usage? If so, can you provide the utility rates Answer 4 Yes, there is no charge. Question 5 For the coating condition survey, please confirm that both tanks will have a coating condition survey requirement. Paragraph 4.1.4 under the API Internal heading references both an interior and exterior coating system survey; however, there is no requirement listed under the API external section. Answer 5 If this project has externals on it the paint sampling is only required when completing an internal, at that time they take samples internally and externally. Question 6 Will isolation kits be required for the new stainless steel manway hardware? If so, redrilling of the flanges and cover plates is likely required to accommodate the 3/4"" bolts and kits. Answer 6 We have never had anyone have to redrill holes for larger bolts/kits. Isolation kits are not required. DLA-Energy has requested USACE to conduct one each Internal and External API inspections at Columbus AFB, MS to inspect facilities in accordance with all laws standards, federal regulations, as well as any state and local regulations and guidelines. API External Inspection Facility #145 API Internal Inspection Facility #141
 
Web Link
SAM.gov Permalink
(https://sam.gov/opp/b7f92b3f77cc4160a21863c1a4b2b323/view)
 
Place of Performance
Address: Columbus, MS 39701, USA
Zip Code: 39701
Country: USA
 
Record
SN07240160-F 20241017/241015230105 (samdaily.us)
 
Source
SAM.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's SAM Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.