SOLICITATION NOTICE
J -- Boiler Steam Safety Valves replaced New Requirement
- Notice Date
- 6/27/2024 5:38:21 AM
- Notice Type
- Combined Synopsis/Solicitation
- NAICS
- 238220
— Plumbing, Heating, and Air-Conditioning Contractors
- Contracting Office
- 248-NETWORK CONTRACT OFFICE 8 (36C248) TAMPA FL 33637 USA
- ZIP Code
- 33637
- Solicitation Number
- 36C24824Q1138
- Response Due
- 7/12/2024 12:00:00 PM
- Archive Date
- 09/10/2024
- Point of Contact
- Jose J Hernandez, Contract Specialist, Phone: 352-381-5708
- E-Mail Address
-
jose.hernandez@va.gov
(jose.hernandez@va.gov)
- Small Business Set-Aside
- SDVOSBC Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14)
- Awardee
- null
- Description
- Boiler Steam Safety Valves replacement The purpose of this amendment is to: 1. Questions provided by contractors are due on July 5, 2024, at 12:00pm. 2. Extend the closing date of solicitation to July 12, 2024. Updated Statement of Work is shown below: Background: The Lake City VA Medical Center in Lake City, Florida has needs to have the Boiler Steam Safety Valves replaced with new cast steel safety valves. The VA is replacing cast iron fittings in the steam system with cast steel fittings. Other deficiencies have been identified and those deficiencies will also be corrected. Objective: Upgrade the boilers at the Lake City VA to clear all deficiencies identified during routine inspection. Scope of Work: Coordinate all work with the Contracting Officers Representative (COR) Replace with new, 6 Combustion Air Flow switches. Two on each boiler. Replace with new, 6 Purge Air Flow switches. Two on each boiler. Replace with new, 2 High Gas Pressure switches (1 natural gas, 1 propane) and install Audible Alarm to ring out in the Plant for both. Replace Boiler 3 Disconnect in VFD Panel. Replace Condensate Pump Control Panel and all the internals in that panel. Replace with new, 4 Boiler estops. One by each door. Replace with new, 2 Pressure Relief Valves for the two reducing stations supplying steam to the DA (cast steel). To include drip pan 90s and the drains run from those 90s. Replace with new, 6 Boiler Steam Safety Valves. Two on each boiler (cast steel). To include drip pain 90s and the drains run from those 90s. Valves shall be sized and installed correctly to meet VA and BEI standards. Re-pipe all 6 Boiler Steam Safety discharge pipes with larger piping. (Piping must be straight and sized correctly for the safety valves they serve to ensure proper steam discharge from plant.) Test all new safety valves to ensure they are functioning are sized correctly. Valves must pass inspection and meet VA compliance once installed and inspected. All Safety valves shall include drip pan 90s and adequate discharge piping to ensure correct operation per VA standard, BEI standard. Core bore and repair the new roof penetrations for the new discharge piping. (roof must be resealed) Discharge the new piping through the roof. Terminate discharge piping at same elevation from roof surface as the existing vents. Set and test all new switches to ensure they are functioning and compliant. Provide all documentation to the COR. Materials: 3 Cast Steel Safety Valves (1 per boiler) Kunkle Model 300 or approved equal Setpoint 145 psi Capacity 6183 lb/hr 3 Cast Steel Safety Valves (1 per boiler) Kunkle Model 300 or approved equal Setpoint 150 psi Capacity 10458 lb/hr 1 Cast Steel Pressure Relief Valve Kunkle Model 300 or approved equal Setpoint 25psi Capacity 2000 lb/hr 1 Cast Steel Pressure Relief Valve Kunkle Model 300 or approved equal Setpoint 60psi Capacity 3700 lb/hr Estops : 4 each 4 pole Emergency Stop Control Stations Pressure Switches: 12 each Antunes Controls JD-2 Red 0.1 24 W.C. Pressure Switch for Gas in to Boiler Plant: 1 each Ashcroft 0-30 psi Condensate Pump Control Panel All components in the box Disconnect Switch for Boiler 3 Qualifications/Certifications: The Contractor Technician shall possess: Technician shall possess at least five years of experience working on Boilers to perform the services listed in the SOW. The contractor and all individuals working on the project site must have taken the OSHA Certified 10-hour safety course. Safety Regulations: All OSHA safety regulations shall be observed during the project. The VA Safety Officer shall have full authority to see that the contractor obeys all safety rules and regulations relative to the fulfillment of this project. Provide the necessary barricades/signage where required. Scheduling and Hours of Work: All work in areas involved shall be scheduled with the COR. The 10 holidays observed by the Federal Government, are New Years Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas or any other day specifically declared by the President of the United States to be a national holiday. Evaluation/Selection Factor: The project must be performed by a contractor that has the capability and capacity to perform the job. Managerial expertise, technical expertise, past performance, and, cost will be considered.
- Web Link
-
SAM.gov Permalink
(https://sam.gov/opp/c2d0965c9b01403fa2f9bd086564bb5c/view)
- Place of Performance
- Address: 619 S. Marion Ave., Lake City, FL 32025, USA
- Zip Code: 32025
- Country: USA
- Zip Code: 32025
- Record
- SN07110349-F 20240629/240627230117 (samdaily.us)
- Source
-
SAM.gov Link to This Notice
(may not be valid after Archive Date)
| FSG Index | This Issue's Index | Today's SAM Daily Index Page |