Loren Data's SAM Daily™

fbodaily.com
Home Today's SAM Search Archives Numbered Notes CBD Archives Subscribe
SAMDAILY.US - ISSUE OF MARCH 27, 2024 SAM #8156
SOLICITATION NOTICE

Z -- FISHER HOUSE RENOVATIONS

Notice Date
3/25/2024 11:00:17 AM
 
Notice Type
Solicitation
 
NAICS
238320 — Painting and Wall Covering Contractors
 
Contracting Office
242-NETWORK CONTRACT OFFICE 02 (36C242) ALBANY NY 12208 USA
 
ZIP Code
12208
 
Solicitation Number
36C24224B0019
 
Response Due
4/4/2024 8:00:00 AM
 
Archive Date
05/04/2024
 
Point of Contact
Lester S Griffith, Contract Specialist
 
E-Mail Address
Lester.Griffith@va.gov
(Lester.Griffith@va.gov)
 
Awardee
null
 
Description
RFI #1 Fisher House Project (1) During the walkthrough it was discussed that the Interior Designer will be selecting furnishes for the Contractor to install: Please provide which materials are being provided by the VA and which materials the Contractor will be purchasing to allow accurate takeoff.  Answer: Designer will be picking out fixtures, tile, paint colors, and any other decorative items needed to support the new furniture. They will need to know from the contractor what brands/price point they have included in your bid so they do not go over budget. (2) Please clarify whether existing furniture will be removed from Fisher House and stored by the VA or whether Contractor will be responsible for moving all furniture from work areas and storing (and whether VA will provide storage or if Contractor is to provide storage). Answer: The VA will NOT provide storage. Storage is on the contractor to provide. (3) Has there been any asbestos testing on tile and existing material; is there any asbestos expected in the Fisher House? Answer: We are testing now. (4) From our understanding the current flooring is engineered so we cannot refinish. Will the current floor in the dining room be replaced with hardwood or LVT? Answer: Dining room flooring is hardwood as is the rest of the first-floor common areas except kitchen. (5) Are they provided with exact models and quantities in the RFI? Answer: Designer will be picking out fixtures, tile, paint colors, and any other decorative items needed to support the new furniture. They will need to know from the contractor what brands/price point they have included in your bid so they do not go over budget. (6) Will the shower be curb less for ADA accessibility? Answer: Yes (7) Will we be required to put up wall art, mirrors, decor accessories, etc.? Answer: Yes (8) Will vent caps get changed? Answer: Yes (9) Will we be required to remove all furniture/fixtures that are currently there? Answer: Yes (10) If so, are they getting disposed of or stored? Answer: Disposition of items is yet to be determined. (11) Are shop drawings required at the time of submission? If so, who will provide the plan? Answer: No, but selected contractor will have to provide submittals for approval. (12) How will payments be processed? (Net 30, after completion, or 20% deposit then rest of payment after completion)? Answer: Progress payments will be authorized as per the percentage of completion according to the schedule of values. (13) What material and fixtures will be purchased by the interior designer and what materials will be purchased by us? Answer: See answer to question #1. (14) Please provide specifications or basis of design for: Prefinished hardwood flooring Ceramic floor tile Wood trim Light fixtures Plumbing fixtures Bathroom vanity Bathroom accessories Glass shower doors Refinishing hardwood floors Answer: Designer will be picking out fixtures, tile, paint colors, and any other decorative items needed to support the new furniture. They will need to know from the contractor what brands/price point they have included in your bid so they do not go over budget.
 
Web Link
SAM.gov Permalink
(https://sam.gov/opp/449615a69f92451e8ff0ad27582091b8/view)
 
Record
SN07007781-F 20240327/240325230052 (samdaily.us)
 
Source
SAM.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's SAM Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.