N -- CSS# 91184 Insulate and Add Additional Heating in Wash Rack Building

Notice Date
3/25/2024 10:29:43 AM
 
Notice Type
Solicitation
 
NAICS
238220 — Plumbing, Heating, and Air-Conditioning Contractors
 
Contracting Office
W6QK ACC-PICA PICATINNY ARSENAL NJ 07806-5000 USA
 
ZIP Code
07806-5000
 
Solicitation Number
W15QKN24Q5044
 
Response Due
3/26/2024 10:00:00 AM
 
Archive Date
03/25/2025
 
Point of Contact
Valetta Love, Phone: 6095625017
 
E-Mail Address
valetta.l.love.civ@army.mil
(valetta.l.love.civ@army.mil)
 
Small Business Set-Aside
SBA Total Small Business Set-Aside (FAR 19.5)
 
Awardee
null
 
Description
***Amendment #2 -Question and Answer Q1. The exterior walls of the Wash Rack Building are finished with corrugated metal panels. Will contractor be required to remove and reinstall interior metal panels for rolled insulation installation? If yes- conduit, receptacles, panels, switchgear, diagonal bracing, heaters, chain fall, and panel trim will need to be removed and reinstalled. Please confirm. If no- please detail how insulation is to be installed. -Insulation can go on over the interior metal diagonal bracing, panel trim, and conduit. Cut out around electrical equipment and seal as if were a seam. Material to be used as stated in the SOW is - The closed cell polyethylene foam with reflective reinforced foil on one side and plastic white finish film on the other side with a minimum insulation value of R15. Q2. Our assumption is all exterior walls are to be insulated; this appears to be more than 2400 SF. Should we price full building square footage or quantity provided in SOW (2400 SF)? Exterior walls are accumulative of 2400 sq ft. Was measured again this morning to confirm. Q3. I just wanted to confirm that there is not a Bid Bond (Guarantee) for the above project bid? As communicated on page 3, Instructions to Offerors - #7 states - The contractor MUST furnish the required Performance and Payment Bonds within 10 Calendar Days after award.
 
Web Link
SAM.gov Permalink
(https://sam.gov/opp/3659f576313c4fe4b76a4b35f2959058/view)
 
Record
SN07007590-F 20240327/240325230051 (samdaily.us)
 
Source
SAM.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's SAM Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.