Loren Data's SAM Daily™

fbodaily.com
Home Today's SAM Search Archives Numbered Notes CBD Archives Subscribe
SAMDAILY.US - ISSUE OF AUGUST 03, 2022 SAM #7551
SOLICITATION NOTICE

J -- FY22: Triennial Electrical Distribution System Testing

Notice Date
8/1/2022 7:27:24 AM
 
Notice Type
Combined Synopsis/Solicitation
 
NAICS
238210 — Electrical Contractors and Other Wiring Installation Contractors
 
Contracting Office
248-NETWORK CONTRACT OFFICE 8 (36C248) TAMPA FL 33637 USA
 
ZIP Code
33637
 
Solicitation Number
36C24822Q1369
 
Response Due
8/15/2022 12:00:00 PM
 
Archive Date
08/30/2022
 
Point of Contact
Brittney Pastore, Contracting Officer, Phone: 813-940-1183
 
E-Mail Address
brittney.pastore@va.gov
(brittney.pastore@va.gov)
 
Small Business Set-Aside
SDVOSBC Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14)
 
Awardee
null
 
Description
FOR OFFICIAL USE ONLY Source Selection Sensitive Information See FAR 2.101 & 3.104 PROPOSAL REQUEST FOR INFORMATION (RFI) FORM SOLICITATION: 36C24822Q1369 FY22: Triennial Electrical Distribution System Testing NOTE: ALL PRE-PROPOSAL INQUIRIES SHALL BE SUBMITTED VIA EMAIL TO brittney.pastore@va.gov BY AN EDITABLE USE OF THIS FORM. Please identify, in numerical sequence, each set of inquiries that you send. Question(s) is/are on the solicitation [ x ] Question(s) is/are on the drawings, specifications, technical data [ ] Company Name and Offeror: The Spanos Group LLC From (person submitting question): __Daniel Rhodes, drhodes@thespanosgroup.com Date of Proposal Inquiry: ___July 28, 2022____________ Phone Number: ___(760) 458-4505______ Proposal Inquiry: (Type inquiry below) Proposal RFI #1 Per Site Visit, confirm that Contractor is only responsible for inspecting, testing, and logging/reporting deficiencies. No equipment and/or circuit breakers shall be replaced. Answer: The previous contract utilized a 10% fee of the contract proposal included in the final cost to cover repairs and replacement of defective parts, breakers, and switches. The contractor secured spare breakers ahead of testing to allow a swap out if the test deemed to remove from service. This prevented a potential life safety situation by re-energizing equipment that has been found defective. This is an advantageous approach for the VA. The VA prefers the contractor to include a plan for this scenario that allows us to stay within Life Safety Code when presented. I refer to the SOW for the actions outside of testing, logging and recording deficiencies. It covers actions required during the process and examples are : Visual and mechanical inspection Check insulation, case, and arc chutes for cracks Lubricate, Clean breaker as necessary and where possible Perform insulation resistance on breaker to ensure proper operation. Perform contact resistance Perform trip time tests on breaker time current devices Exercise and operate the breaker to ensure proper operation Clean and inspect breaker cell, interlocks and racking mechanism Each type of breaker has its own certification requirements in the SOW Proposal RFI #2 Per Site Visit, confirm that the last system testing cycle did not finish inspecting and testing all the circuit breakers and Contractor should attempt, scheduling permitting, to start testing where the last testing cycle finished. Answer: The previous testing schedule should not affect this effort. The schedule should be driven by the difficulty of isolating the breaker being tested. This can be defined on the first project coordination meeting. Some breakers will need longer to schedule and more preparation by the facility. The assumption is that the breakers that did not get accomplished were the most difficult to isolate. Proposal RFI #3 Per Site Visit, previous testing cycles reflect that Contractor was not able to finish inspecting and testing all the circuit breakers within scope, primarily due to the inability of various VA departments not being able to schedule or accommodate Contractor testing schedules. In the event Contractor experiences similar circumstances with the inability in scheduling and/or conducting the inspections/tests in scope, please confirm that Contractor s scope shall be deemed completed for purposes of fulfilling the Contractual Requirements? Answer: The contractor will not be required to perform any actions on that equipment that depends on the power to be removed to complete, only if the VA determines that the power cannot be secured. The less evasive actions such as inspection and infra-red actions should still be accomplished and everything that was not done shall be logged and in the final report. Proposal RFI #4 Per Site Visit, some circuit breakers within scope are SquareD. Does a SquareD representative need to be onsite during Contractor testing? Answer: Historically the Eaton representatives are qualified and certified by the International Electrical Testing Association (NETA) or equivalent certifying organization as Certified Technicians to perform the maintenance on other manufacturers equipment. Since the vast majority is Eaton it is preferred. Proposal RFI #5 Per Site Visit, can the VA share who would typically be involved in Contractor s scheduling coordination, outside of the VA COR engineers delegated to the project? For example, certain department heads, facilities personnel, etc. Answer: Generally, the Electric O&M Shop will be deeply involved. Any others affected will be involved in coordination. Removing power to any area on this hospital campus requires coordination. Proposal RFI #6 Can the VA provide Contractor with example Summary Reports from previous testing cycle projects? Particularly if the VA believes previous summary report formats should be followed for this new project. Answer: This is generally a newer requirement being performed here. Unfortunately, we do not have a report that incorporates the required information in the SOW from the last project. If the contractor has technical training and demonstrable track records of working experience in maintenance, inspection, and testing of the Electrical Power Distribution Systems and related components in healthcare as required by the SOW, then they should be familiar or able to source the format. Proposal RFI #7 - Per Site Visit, it was relayed that due to physical space constraints in various electrical rooms and locations of circuit breakers that Contractor should expect to have only one (1) Contractor representative onsite during various scheduled inspections/testing (the Superintendent, for example). Please confirm. Answer: I do not recall any conversation of this manner. The contractor is required to perform the service within VA Safety and OSHA Guidelines. The service performance is never to only have one person performing any action. All of these actions are inherently dangerous and requires a Superintendent, Safety Representative and utilize NFPA trained Qualified personnel as required by the SOW under Qualifications of contractors. All certifications shall be reviewed prior to work commencing.
 
Web Link
SAM.gov Permalink
(https://sam.gov/opp/fad0376e6d634b4581755d482d900ab4/view)
 
Place of Performance
Address: Department of Veterans Affairs James A. Haley Veterans Hospital 13000 Bruce B. Downs Blvd., Tampa, FL 33612, USA
Zip Code: 33612
Country: USA
 
Record
SN06408890-F 20220803/220801230127 (samdaily.us)
 
Source
SAM.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's SAM Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.