SOURCES SOUGHT

56 -- Repair Hangar Doors

Notice Date
9/12/2019
 
Notice Type
Sources Sought
 
NAICS
561210 — Facilities Support Services
 
Contracting Office
Department of the Army, National Guard Bureau, USPFO AL 117 MSC, 5401 E LAKE BLVD, BIRMINGHAM, Alabama, 35217-3595, United States
 
ZIP Code
35217-3595
 
Solicitation Number
BRKR192007
 
Archive Date
10/2/2019
 
Point of Contact
Jeffrey A. Farmer, Phone: 2057142347, William K. Hall, Phone: 2057142248
 
E-Mail Address
jeffrey.farmer.2@us.af.mil, william.k.hall14.mil@mail.mil
(jeffrey.farmer.2@us.af.mil, william.k.hall14.mil@mail.mil)
 
Small Business Set-Aside
Total Small Business
 
Description
STATEMENT OF WORK REPAIR HANGAR DOOR SEALS SRM PN BRKR 192007 BIRMINGHAM IAP (ANG) ALABAMA 7 Sep 2019 SUMMARY OF WORK PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and General Requirements (if any) apply to the work specified in this section. 1.2 DESCRIPTION OF WORK A. This project provides for the removal and replacement of vertical hangar door seals at buildings 135 and 138 according to manufacturer’s recommendations. B. Provide for traffic and personnel safety at all times as base personnel work is in progress over nights, weekends, etc. 1.3 CONTRACT RESPONSIBILITIES A. The work is one contract bid package that will be contracted directly with the CONTRACTING OFFICER. B. Responsibilities of CONTRACTOR: 1. Except as specifically noted, provide and pay for: a) Labor, materials, and equipment. b) Tools, construction equipment and machinery. c) Other facilities and services necessary for proper execution and completion of work (locating and flagging underground utilities, etc.) d) Independent testing lab to do all materials and quality control testing. e) “Provide” means to furnish and install, complete and ready for operation. 2. Give required notices. 3. Comply with codes, ordinances, rules and regulations, orders and other legal requirements of public authorities which bear on performance of work. 4. Promptly submit written notice to CONTRACTING OFFICER of observed variance of contract documents from legal requirements. a) Assume responsibility for work to be contrary to such requirements, without notice. b) Appropriate modifications to Contract Documents will adjust changes necessary due to legal requirements. 5. Enforce strict discipline and good order among employees. Do not employ on work: a) Unfit persons. b) Persons not skilled on assigned tasks. 6. Furnish all submittals (including shop drawings, catalog cuts, brochures, test reports, progress schedules, estimates and general correspondence) promptly and on time to be approved before starting the work for which submittals are required. C. Responsibilities of CONTRACTING OFFICER: 1. CONTRACTING OFFICER to review materials testing lab qualifications submitted by the CONTRACTOR. 2. Construction Drawings. 1.4 CONTRACTOR USE OF PREMISES A. Confine operations at site to areas permitted by: 1. Law 2. Ordinances 3. Permits 4. Contract Documents 5. Existing Staging Areas 6. Where directed by CONTRACTING OFFICER. B. Do not unreasonable encumber site with materials or equipment. C. Assume full responsibility for protection and safekeeping of products stored on premises. D. Move any stored products which interfere with operations of CONTRACTING OFFICER or other CONTRACTORS engaged in work for the CONTRACTING OFFICER. E. Use of Site: Government will occupy the site during construction. Coordinate so that the least amount of disruption is caused, that traffic and personnel safety is maintain. F. CLEANLINESS IS THE ESSENCE OF QUALITY. Keep site clean. Remove waste material from the site weekly. Failure to comply will result in notice to clean site given by CONTRACTING OFFICER; if not cleaned within twelve (12) hours from time of notice, the CONTRACTING OFFICER will clean the site and charge the CONTRACTOR $100.00/hour for this work. 1.5 SUBMITTALS A. Approval for all materials must be given before installation. B. No work can be started until such work has been discussed and reviewed by the CONTRACTING OFFICER C. Test reports shall be checked by the CONTRACTING OFFICER to insure compliance with the Specifications. 1. Any deviations will be made known to the CONTRACTOR and CONTRACTING OFFICER. 2. It is the CONTRACTOR’S responsibility to achieve compliance with the Specifications. 1.6 ITEMS OF WORK- NOT TO BE USED FOR BIDDING PURPOSES!!! Qty Description Unit 220 Vertical Rubber Seals LF 220 Pressure sensing electric strips safety edge LF 3 Manlift Rental week 557 Screws, bolts, fasteners Lb 1 Installation of above items LS 1 Troubleshooting, Warranty Checkout LS PART 2 PRODUCTS Seals, pressure sensors, fasteners, lift rental, installation and warranty of all items. PART 3 EXECUTION To be scheduled when hangars are vacant or when work won’t interfere with contractor or aircraft. PART 4 PERFORMANCE PERIOD The performance period for this contract is 90 days. END OF DOCUMENT
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/notices/dd4e8c5d03c1023546af4f61b53d48f0)
 
Place of Performance
Address: 117 ARW/MSC, 5401 East Lake Blvd, Birmingham, Alabama, 35217, United States
Zip Code: 35217
 
Record
SN05441843-W 20190914/190912231008-dd4e8c5d03c1023546af4f61b53d48f0 (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.