AWARD

Y -- Building 20423 HVAC Install, KAFB

Notice Date
7/13/2018
 
Notice Type
Award Notice
 
Contracting Office
Department of the Army, U.S. Army Corps of Engineers, USACE District, Albuquerque, Attn: CESPA-CT, 4101 Jefferson Plaza NE, Albuquerque, New Mexico, 87109-3435, United States
 
ZIP Code
87109-3435
 
Solicitation Number
W912PP17Q0079
 
Archive Date
7/27/2018
 
Point of Contact
Glenda D. Kohlieber, Phone: 5756524135
 
E-Mail Address
glenda.d.kohlieber@usace.army.mil
(glenda.d.kohlieber@usace.army.mil)
 
Small Business Set-Aside
N/A
 
Award Number
W912PP18P0053
 
Award Date
7/12/2018
 
Awardee
ORCOM, 2206 SUN RANCH VILLAGE LOOP, LOS LUNAS, New Mexico 87031, United States
 
Award Amount
$149528.74
 
Line Number
0001
 
Description
This action was awarded as an 8(a) Sole Source Set-Aside under the authority of section 8(a) of the Small Business Act. The contractor shall furnish all parts, material, labor, equipment and supervision necessary to complete the work for Building 20423 HVAC Installation. 2. SPECIFIC REQUIREMENTS: 1.Room 306: i.Contractor to install 0.6 ton round flow sensing cassettes units to provide heating and cooling. ii.Relocate existing sensors and lights as needed. iii. Adjust the ceiling grid and ceiling tiles once the HVAC unit is installed. iv.Remove the existing diffusers and grilles and cap duct. 2.Room 307: i.Contractor to install a 1 ton round flow sensing cassette unit provide heating and cooling. ii.Relocate sensors and lights as needed. iii.Adjust existing ceiling grid and tiles once the HVAC unit is installed. iv.Remove existing diffusers and grilles and cap duct. 3.Room 308: i. Contractor to install 0.6 ton round flow sensing cassette unit to provide heating and cooling. ii.Relocate sensors and lighting as needed. iii.Adjust existing ceiling grid and ceiling tiles once HVAC unit is installed. iv.Remove existing diffusers and grilles and cap duct. 4.Room 309: i.Contractor to install four (4) 1 ton round flow sensing cassette unit to provide heating and cooling. ii.Relocate sensor and lighting as needed. iii.Adjust existing ceiling grid and tiles once the HVAC unit is installed. iv.Remove existing diffusers and grilles and cap duct. 5.Room 310: i.Contractor to install 1.5 ton round flow sensing cassette unit to provide heating and cooling. ii.Relocate sensor and lighting as needed. iii.Adjust existing ceiling grid and tiles once HVAC unit is installed. iv.Remove existing diffusers and grilles and cap duct.   6.Room 311: i.Contractor to install 1 ton round flow sensing cassette unit to provide heating and cooling. ii.Relocate sensor and lighting as needed. iii.Adjust existing ceiling grid and tiles once HVAC unit is installed. iv.Remove existing diffusers and grilles and cap duct. 7. Room 312: a. Contractor to install 1 ton round flow sensing cassette unit to provide heating and cooling. b. Relocate sensors and lighting as needed. c. Adjust existing ceiling grid and tiles once HVAC unit is installed. d. Remove existing diffusers and grilles and cap duct. 8. Room 313: a. Contractor to install 1.5 ton round flow sensing cassette unit to provide heating and cooling. b. Relocate sensors and lighting as needed. c. Adjust existing ceiling grid and tiles once HVAC unit is installed. d. Remove existing diffusers and grilles and cap duct. 9. Rest Room 323: a. Contractor to install 0.5 ton wall mounted unit for heating and cooling. b. Remove existing diffuser and grilles and cap duct patch ceiling opening and repair to match existing ceiling. 10. Room 326: a. Contractor to install (1) 1 ton and (1) 0.75 ton round flow sensing cassette units to provide heating and cooling. b. Relocate sensors and lighting as needed. c. Adjust existing ceiling grid and tiles once HVAC unit is installed. d. Remove existing diffusers and grilles and cap duct. 11. IT Room: a. Contractor to install 1.5 ton wall mounted unit for cooling. b. Remove existing diffusers and grilles and cap duct. 12. Contractor to install thermostats at every location with a cassette unit. 13. Install one condenser on the outside of the building. 14. Install a concrete pad with a stand for the condenser to rest on. 15. Install an enclosure for the lines along the wall. Match the building color. 16. Install one VRV, location to be determined at a later date. 17. Connect the HVAC systems to the existing I-Touch Manager.  
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA47/Awards/W912PP18P0053.html)
 
Record
SN04990935-W 20180715/180713230802-967e9703ee64bd5d0d502efff20ad3a6 (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.