MODIFICATION

71 -- Small Arms Storage System

Notice Date
8/4/2017
 
Notice Type
Modification/Amendment
 
NAICS
337127 — Institutional Furniture Manufacturing
 
Contracting Office
Department of the Army, National Guard Bureau, USPFO for Oregon, Attn: USPFO-P, PO Box 14840, Salem, Oregon, 97309-5008
 
ZIP Code
97309-5008
 
Solicitation Number
W912JV-17-Q-7020
 
Archive Date
8/26/2017
 
Point of Contact
Joel Sire, Phone: 541-885-6181
 
E-Mail Address
joel.a.sire.mil@mail.mil
(joel.a.sire.mil@mail.mil)
 
Small Business Set-Aside
Total Small Business
 
Description
QUESTION: Do you have a drawing of the space available? ANSWER: No. The room dimensions are 22'0" X 25'0". QUESTION: Is floor covering required on the 3/4" plywood flooring? ANSWER: Yes, toughdeck (or equal) is an anti-skid surface for safety purposes. QUESTION: The system says surface mounted, leveled tracks but then notes anti-tip brackets. As Oregon is in a seismic zone, only anchored systems will meet seismic zone requirements. Are the tracks for the carriages to be anchored to the concrete slab? ANSWER: The decking is mounted to the floor and the tracks are part of the decking. No concrete or floor cutting. Unit will include seismic tethering. The system will be anchored to the concrete slab. QUESTION: Are full height steel end panels required at the front of each carriage? ANSWER: Not necessary, but due to triple-lock down security measures that all military branches require for weapons, this system utilizes closed panels all the way around the unit with a mobile lock. End user requested component possess the capability to close like a box for securing purposes, meaning no racks exposed (key locked). QUESTION: What is the height of the fire sprinklers in the armory from the concrete slab? ANSWER: The clear ceiling height is 9' is 108" (as noted), with drop down sprinklers QUESTION: Most weapon racks installed on top of mobile carriages leave a total installed height of 91", which does not meet fire code. Is this allowable? ANSWER: The Kingsley field Civil Engineer will grant a waiver if the height exceeding code is minimal and adequate fire protection can still be provided. QUESTION: the V Grip Bulk Rack, how many shelves per section are required? Are all 3 sections connected or are they separate? A drawing would help illustrate the shelving layout. ANSWER: End user requested 4-levels of wire decking per unit with the ability to adjust shelving on 1.5" centers (adjustable). Safety - Wire decking for lighting and fire suppression. The Bulk racks will store 16 Pelican cases (44.90" L x 25.32" W x 16.5 "H). Each case will hold 12 M16/ M4 rifles. Each rifle weighs approximately 5-10lbs. The 4 shelves need to be 8' x 8' and 24" deep to hold the pelican cases. QUESTION: Can you provide a list with quantities of each type of weapon to be stored? ANSWER: End user based weapons racks count on current on hand and/or anticipated weapon count. There are 340+ M16/M4 and 130+ 9MM QUESTION: Can you advise if retractable doors on the weapon racks is a must-have or if bi-folding (non-retractable) doors will be sufficient? ANSWER: Not necessary, however, end user prefers retractable doors due to traffic flow and safety measures. Clearance between racks when carriage is open is 3.5'. QUESTION: Will only the 18 weapons cabinets will be mounted to the high density mobile storage system? ANSWER: Correct. QUESTION: What is the number of shelves per unit for the VGrip Bulk Rack? ANSWER: 4-Level, heavy duty wire decking adjustable on 1.5" centers. Meaning beam levels can be adjusted every 1.5"s if customer desires to adjust levels in the future. QUESTION: Is the infill floor between the tracks plywood with non-skid tuff deck or resin deck required? Or do you just want unfinished plywood? ANSWER: Toughdeck with anti-skid for safety measures. QUESTION: Do the weapon cabinets, mechanical mobile system, bulk rack and work bench need to be from one manufacturer? Not necessary, but end user preferred turn-key solution that matched warranty for all products. ANSWER: No, but all components must be compatible and maintain full functionality. QUESTION: Is installation required? ANSWER: Yes.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/NGB/DAHA35/W912JV-17-Q-7020/listing.html)
 
Place of Performance
Address: Kingsley Field, Klamath Falls, Oregon, 97603, United States
Zip Code: 97603
 
Record
SN04613833-W 20170806/170804231906-c636c0d84fc8d3e75ccd4cfb9835202b (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.