SPECIAL NOTICE
Y -- Project Labor Agreement Notice for Port Monmouth, NJ Phase II-Contract 4
- Notice Date
- 12/21/2016
- Notice Type
- Special Notice
- NAICS
- 237990
— Other Heavy and Civil Engineering Construction
- Contracting Office
- Department of the Army, U.S. Army Corps of Engineers, USACE District, New York, Attn: CENAN-CT, 26 Federal Plaza, New York, New York, 10278-0090, United States
- ZIP Code
- 10278-0090
- Solicitation Number
- W912DS-17-S-0007
- Point of Contact
- Alex Heinzel, Phone: 9177908087
- E-Mail Address
-
alexander.t.heinzel@usace.army.mil
(alexander.t.heinzel@usace.army.mil)
- Small Business Set-Aside
- N/A
- Description
- The Corps of Engineers New York District is soliciting comments from the construction community addressing the potential use of a Project Labor Agreement (PLA) for the following large scale (exceeding $25 million) construction project: Hurricane and Storm Damage Reduction Project, Raritan Bay and Sandy Hook Bay, Port Monmouth, NJ, Phase II - Contract 4. PROJECT DESCRIPTION Contract 4 includes construction of approximately 3,871 linear feet of concrete floodwall (T-wall section). The floodwall will vary in height above the existing ground surface to elevation +13.0 ft NAVD 88. The floodwall tie-off to high ground will require regrading of State Route 36 that is under NJDOT jurisdiction (80 linear feet on the northbound side and 125 linear feet on the southbound side) and regrading a property along Wilson Avenue. There will be about 1,080 linear feet of levee having 2.5:1 side slopes with a height that varies above the existing ground surface to elevation +13.0 ft NAVD 88. The levee top width will be 10 feet wide and the entire levee section will be seeded with grass. Drainage swales will be constructed along the levee/floodwall to convey interior drainage water to drainage outlet structures. This contract includes installing two steel roller gate closure structures across roadways. One road closure gate, 57 feet long by 8.9 feet high will be installed on Campbell Avenue. The other road closure gate, 35 feet long by 7.8 feet high, will be installed across Broadway. The road gate work includes installation of electric winches, lighting, and signage. The floodwalls and road closure gates will be supported on steel H-pile foundations and a sheet pile cutoff wall will extend beneath their base. The Henry Hudson Trail will be re-routed through Campbell Avenue. Utility relocations include overhead electric and telecommunications poles and lines, and underground water, gas, and sanitary sewer mains. Additional project features include fencing, soil erosion and sediment control measures and landscaping. Range of Magnitude: Between $25,000,000.00 and $100,000,000.00. Period of Performance: Approximately 640 calendar days after Notice to Proceed. Notice to Proceed is anticipated to occur in June 2017. A PLA is defined as a pre-hire collective bargaining agreement with one or more labor organizations that establishes the terms and conditions of employment for a specific construction project and is an agreement described in 29 U.S.C. 158(f). Some of the factors that may be considered regarding PLA use are: a. The project will require multiple contractors and/or subcontractors working in multiple crafts or trades. b. There is a shortage of skilled labor in the region. c. Completion of the project will require an extended period of time. d. PLA's have been used on comparable projects undertaken by Federal, State, municipal, or private entities in this geographic area. e. A PLA will promote the agency's long term program interests, such as training of skilled workforce to meet the agency's future construction needs. Federal Acquisition Regulation (FAR) Policy: a. Project Labor Agreement (PLA) is a tool that agencies may use to promote economy and efficiency in Federal procurement. Pursuant to Executive Order 13502, agencies are encouraged to consider requiring the use of project labor agreements in connection with large-scale construction projects. b. An agency may, if appropriate, require that every contractor and subcontractor engaged in construction on the project agree, for that project, to negotiate or become a party to a project labor agreement with one or more labor organizations if the agency decides that the use of project labor agreements will: (1). Advance the Federal Governments interest in achieving economy and efficiency in Federal procurement, producing labor-management stability, and ensuring compliance with laws and regulations governing safety and health, equal employment opportunity, labor and employment standards, and other matters; and (2). Be consistent with law. Reference: Provision: 52.222-33 Notice of Requirement for Project Labor Agreement and 52.222-34 Project Labor Agreement. In consideration of the above factors, and any others which may be deemed appropriate, the construction community is invited to comment on the use of a PLA. Of particular interest to the Government are responses to the following questions: 1.Have comparable projects been undertaken by Federal, State, municipal, or private entities in the geographic area of this project? Do you have knowledge that a PLA has been used in the local area on similar projects? If so, please provide supporting documentation. For each project, please indicate if a PLA was used, if available, the initial and final cost, number of trades on the project, if the project was completed on time, and if there were any challenges such as labor shortages, labor related delays, safety issues, etc. 2.Are you aware of skilled labor shortages in the area for those crafts that will be needed to complete the referenced projects? These projects will require construction contractors and/or subcontractors employing workers in multiple crafts or trades. Do you foresee any work on these projects that may result in both the prime contractor and at least one subcontractor, or two or more subcontractors, employing the same trade? Are there concerns by prime contractors on the availability of skilled construction labor? Are there large scale construction projects in the area (over $25M, within 50 miles of Port Monmouth) which could impact availability of skilled labor for the referenced projects? What is the anticipated volatility in the labor market for the trades required for the execution of the projects? Are existing apprentice programs providing sufficient numbers of skilled workers for future requirements? If so, please elaborate and provide supporting documentation where possible. 3. Are you aware of time sensitive issues/scheduling requirements that would impact the rate at which the referenced projects should be completed? If so, please elaborate and provide supporting documentation where possible. Is the proposed schedule/completion time one which would benefit from a PLA - if so, how? Will a PLA impact the completion time? How would a PLA benefit a project which contains a unique and compelling mission-critical schedule? 4.Identify specific reasons why or how you believe a PLA would advance the Federal Government's interest in achieving economy and efficiency in federal procurement. Are there any other economies or efficiencies derived by the Federal Government, if using a PLA? 5.Identify specific reasons why you do not believe a PLA would advance the Federal Government's interest in achieving economy and efficiency in federal procurement. 6.Are there any concerns regarding labor-management stability related to the referenced projects? Will the use of a PLA produce labor-management stability on these projects? Have labor disputes or other labor issues contributed to project delays in the local area? Are you aware of examples of labor-management conflicts in the area which could impact the efficiency of these projects, which a PLA could positively impact/resolve? What market share does union labor in construction trades have in the geographic area? Which existing Collective Bargaining Agreements will expire during construction of the referenced projects? 7.Will use of a PLA be conducive to ensuring compliance with laws and regulations governing safety and health, equal employment opportunity, labor and employment standards, and other relevant matters on these projects? Are there instances where these standards have not been met on Federal contracts in the local area? Were PLAs used for those specific contracts? 8.What is the estimated relative cost impact of using a PLA? Will a PLA impact the cost of submitting an offer? 9.Will the use of a PLA impact the ability of potential bidders and subcontractors to meet small-business utilization goals? Should a PLA be executed on the above described Port Monmouth Phase II- Contract 2? What benefits do you believe a PLA could achieve? What other factors should the Corps consider before deciding whether to include PLA provisions for Port Monmouth Phase II- Contract 2? 10.Please identify any additional information you believe should be considered on the use of a PLA on the referenced project. Please provide your comments via e-mail to Alex Heinzel, Contract Specialist at alexander.t.heinzel@usace.army.mil no later than 2:00 PM on 20 January 2017. This is NOT a Request for Proposal and does not constitute any commitment by the Government. Responses to this labor market survey will be used by the Government to make appropriate acquisition decisions. All interested sources must respond to future solicitation announcements separately from responses to this market survey.
- Web Link
-
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA51/W912DS-17-S-0007/listing.html)
- Place of Performance
- Address: Port Monmouth, Middletown Township, New Jersey, 07758, United States
- Zip Code: 07758
- Zip Code: 07758
- Record
- SN04357626-W 20161223/161221234826-0a13774d565cf2beca1df8e925466d3a (fbodaily.com)
- Source
-
FedBizOpps Link to This Notice
(may not be valid after Archive Date)
| FSG Index | This Issue's Index | Today's FBO Daily Index Page |