Z -- Big Bend Gear Box rehab - Solicitation 1

Notice Date
10/31/2016
 
Notice Type
Modification/Amendment
 
NAICS
237990 — Other Heavy and Civil Engineering Construction
 
Contracting Office
Department of the Army, U.S. Army Corps of Engineers, USACE District, Omaha, Attn: CENWO- CT, 1616 Capitol Ave, Omaha, Nebraska, 68102-4901, United States
 
ZIP Code
68102-4901
 
Solicitation Number
w9128f-16-R-0091
 
Response Due
11/30/2016 2:00:00 PM
 
Point of Contact
patrick mally, Phone: 4029952070
 
E-Mail Address
patrick.j.mally@usace.army.mil
(patrick.j.mally@usace.army.mil)
 
Small Business Set-Aside
Total Small Business
 
Description
Solicitation SOLICITATION NO. W9128F-17-R-0006 On or about 25 July 2016, this office will issue Request for Proposals for construction of the Intake Gate Gear Box Refurbishment and Feeder, Big Bend Dam, SD. The solicitation will close on or about 25 August 2016. This solicitation is RESTRICTED TO SMALL BUSINESS PARTICIPATION. A site visit date and time will be issued with the advertisement package. DO NOT submit requests for plans and specifications to the site visit personnel listed above. See ‘Obtaining Solicitation Documents' below. _______________________________________________________________________________ Project Description: The powerhouse intake gate hoist gearboxes are located on the deck of the intake structure of the Big Bend dam, Fort Thompson, South Dakota. Each gate hoist and gearbox assembly is designed to raise a rated load of 69 tons a total distance of 78 feet at the rate of two (2) feet per minute and to lower this load at the rate of four(4) feet per minute. Each gearbox (gear reducer) is driven by an electric motor (15hp, two speeds) with input speed of 842 rpm. Output torque of the gearbox is 126,000 inch lb. The work includes providing and installing of three (3) new sets of gearboxes and refurbishing all twenty four (24) existing gear boxes at the gear manufacturer's facility. The refurbishing work is to be executed subsequently by removing and refurbishing three (3) sets of gearboxes at a time in order to minimize the interruption of powerhouse operation. Refurbishment will include repainting gearbox housing, replacement of all gearbox components including but not limited to bearing, shim, worm and helical gear, output shaft, gearbox oil, oil heater and thermostat. Contractor is to obtain necessary permits to dispose existing gearbox oil. Replacement will also include feeder and breaker replacement. Currently, there are two #4/0 3 phase feeders that feed all 24 gear boxes. They will be replaced in kind with water proofing. The breakers are currently mechanically interlocked and will be replaced with keyed interlocked breakers. The estimated construction cost of this project is between $1,000,000 and $2,500,000. Questions regarding contractual matters should be made to: Patrick Mally 402 995 2070.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA45/w9128f-16-R-0091/listing.html)
 
Place of Performance
Address: Big Bend dam, Fort Thompson, South Dakota, Fort Thompson, South Dakota, United States
 
Record
SN04316205-W 20161102/161031234042-24b2c80108d7ad6aa6bcf3eb20061585 (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.