N -- BONNEVILLE SECOND POWERHOUSE POTENTIAL TRANSFORMER UPGRADE

Notice Date
10/2/2014
 
Notice Type
Award Notice
 
NAICS
238210 — Electrical Contractors and Other Wiring Installation Contractors
 
Contracting Office
USACE District, Portland, Contracting Division (CECT-NWP), P.O. Box 2946, Portland, OR 97208-2946
 
ZIP Code
97208-2946
 
Solicitation Number
W9127N-14-R-0030
 
Response Due
9/5/2014
 
Archive Date
11/1/2014
 
Point of Contact
Jeffrey Renner, 503.808.4630
 
E-Mail Address
USACE District, Portland
(jeff.s.renner@usace.army.mil)
 
Small Business Set-Aside
N/A
 
Award Number
W9127N-14-C-0037
 
Award Date
9/30/2014
 
Awardee
BURKE ELECTRIC, L.L.C. (027354265) <br> 13563 SE 27TH PL <br> BELLEVUE, WA 98005-4212
 
Award Amount
$1,402,791.00
 
Line Number
0001-0010
 
Description
The purpose of this project is to improve main unit circuit breaker synchronization by moving the synchronizing signal from the 230kV side of the GSU transformers to the 13.8kV side of the GSU transformers at the Bonneville Second Powerhouse in Skamania County, Washington. The existing signal on the grid side of the main unit circuit breakers comes from bushing potential transformers on the 230kV side of the GSU transformers. In order to get the same signal to the 13.8kV breaker synchronizing equipment without the small error introduced by the transformation through the GSU transformers, new 13.8kV potential transformers are required on the 13.8kV side of the GSU transformers. This project covers all work required to furnish, install, commission, and place in service the new 13.8kV synchronizing potential transformers at the Bonneville Second Powerhouse. This includes but is not limited to furnishing and installing four new potential transformer cubicles rated 13.8kV, complete with potential transformers, new isolated-phase bus from the cubicles tapping into the existing runs of isolated-phase bus, control wiring from the new cubicles to the existing main unit generator control boards, rewiring inside the control boards, and verifying and updating the control board wiring diagrams. Work must be performed over limited outages in two consecutive years.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA57/W9127N-14-R-0030/listing.html)
 
Record
SN03541403-W 20141004/141002235301-f96babbd058d4ecf53be509e09fb2731 (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.