MODIFICATION

F -- Road 103 Culvert Installation - Amendment 1

Notice Date
9/2/2014
 
Notice Type
Modification/Amendment
 
NAICS
115310 — Support Activities for Forestry
 
Contracting Office
Department of Agriculture, Forest Service, R-1 IMAT: Clearwater; Idaho Panhandle; Kootenai; and Nez Perce NF's, 3815 Schreiber Way, Coeur d'Alene, Idaho, 83815-8363, United States
 
ZIP Code
83815-8363
 
Solicitation Number
AG-02RC-S-14-0040
 
Response Due
9/5/2014 2:30:00 PM
 
Point of Contact
Darren M. Zychek, Phone: 2084768224
 
E-Mail Address
dzychek@fs.fed.us
(dzychek@fs.fed.us)
 
Small Business Set-Aside
Total Small Business
 
Description
Amendment 001 - Pre bid tour notes. Pre-bid Tour Points of Clarification for 15 August 2014: 1.) Typically due to late snow melt in the Beaver Dam Saddle vicinity the culvert replacement sites are not accessible until between July 1 and July 15 on the average year. 2) To Clarify culverts to be replaced at milepost 21.20, 22.60, and 24.60 will be stream crossing and shall be installed in accordance to the stream crossing detail on sheet 3. All other culverts will be installed in accordance to the "Typical HDPE Installation in Cut Section" detail on sheet 3 and will require the class 4 rip rap at the outlet. 3) Excavation quantities we determined by calculating the in place excavation using the average end area method. A typical trench cross section had a 3' tall vertical walled trench at the bottom near the pipe that was the pipe diameter plus 30" wide. After, the three foot vertical wall the trench was excavated at a 1 foot horizontal to 1 foot vertical slope in accordance with OSHA trenching guidelines. If the contractor chooses to excavate outside the typical trench detail described above all additional excavation will be incidental and will not constitute additional excavation quantity. Time Extension: New closing date: 15 September 2014
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/USDA/FS/281/AG-02RC-S-14-0040/listing.html)
 
Place of Performance
Address: The project site is located between mileposts 20 and 26 on USFS Road 103. From U.S. Highway 12, turn north onto State Highway 11, at Greer Junction. Travel north on State, Highway 11 to Weippe, ID. When State Hwy 11 turns a hard left in Weippe, go straight taking the Musselshell Road. Take the Musselshell Road for approximately 8 miles to the junction of USFS 100 at Perterson’s corner. Go straight at the junction onto USFS 100 and travel towards Kamiah for approximately 5.8 miles to the junction of USFS Road 103. Turn left onto USFS 103 and travel to the sites as staked at mile posts 20.89, 21.20, 21.60, 21.80, 21.82, and 22.60, Orofino, Idaho, 83544, United States
Zip Code: 83544
 
Record
SN03492455-W 20140904/140903000124-59a18ad798830aeff5427f6a78e6bdc7 (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.