MODIFICATION
Y -- MAIN CIRCUIT BREAKER/STATIC FREQUENCY CONVERTER
- Notice Date
- 8/8/2011
- Notice Type
- Modification/Amendment
- NAICS
- 237990
— Other Heavy and Civil Engineering Construction
- Contracting Office
- USACE District, Savannah, P.O. Box 889, Savannah, GA 31402-0889
- ZIP Code
- 31402-0889
- Solicitation Number
- W912HN-11-R-0040
- Response Due
- 8/24/2011
- Archive Date
- 10/23/2011
- Point of Contact
- Scott T. Freas, Phone: 9126525180
- E-Mail Address
-
scott.t.freas@usace.army.mil
(scott.t.freas@usace.army.mil)
- Small Business Set-Aside
- Total Small Business
- Description
- This acquisition is being solicited as a Total Small Business Set-Aside. The government is using the Performance Price Trade-Off Process. The magnitude is between $10M and $25M. The resultant contract will be firm-fixed price. The contract may include options. Description of work: This project is to perform the work required for the replacement of the existing main unit circuit breakers (MCBs) for Units 1-8 with new Government-Furnished SF6 15 kV MCBs, replacement of the existing static excitation systems for Units 5-8 with new Government-Furnished static excitation systems, and to complete installation of a new Government-furnished static frequency controller (SFC) system at the Richard B. Russell Powerhouse. Perspective contractors should be regularly engaged, for a minimum of three consecutive years, in the assembly, installation, and testing of high voltage power generation and/or transmission equipment of similar type and rating as the Government furnished circuit breakers and other equipment outline below. Descriptive specifications and plans will be provided; however, the work may require substantial engineering capabilities in order to successfully complete the work. The Richard B. Russell Powerhouse contains four 4000 ampere air blast circuit breakers, one for each of the 13.8 kV main unit generators, units 1-4 and four 5000 ampere air blast circuit breakers, one for each of the 13.8 kV main unit generators, units 5-8. Work includes, but is not limited to: removal of the eight (8) main unit circuit breakers (MCBs), eight (8)disconnects, control equipment and enclosures; removal of control cables to the Generator Actuator cabinets and Excitation cubicles in the Generator Bays and Switchgear Rooms and to the Main Control Panels in the Powerhouse Control Room; partial removal of isolated-phase bus and supports; removal of the air compressor; installation of eight (8) Government-furnished SF6 circuit breakers, control cabinets and isolated-phase bus (IPB) and supports, including cable; complete the installation of the Government-furnished static frequency controller (SFC) system, input and output circuit breakers and transformers, two (2) current-limiting reactors, and isolated-phase bus; conduits; medium voltage cables and control cables and terminations; and the miscellaneous electrical accessories. Optional items include additional hired labor, welding, installation of eight (8) three-phase disconnect switches for MCBs, installation of two (2) three-phase disconnect switches for in isolated-phase bus to the SFC current limiting reactors. The contractor may write a proposal to modify existing Government-furnished isolated-phase bus instead of providing new isolated-phase bus. If approved, the Government-furnished isolated-phase bus shall be installed at the exterior of Units 5 - 8 to accommodate the installation of the SF6 breakers, as well as the interior portion of Unit 8 and the exciter taps for the Current-Limiting Reactor banks at Units 6 & 7. This solicitation will be issued in electronic format only. Paper copies of this solicitation will not be available. Other methods of requesting a package will not be honored. Offerors must register in the Central Contractor Registration (CCR) at www.ccc.gov. After completing CCR, in order to download RFP documents contractors and their subcontractors must register at www.fbo.gov. Contractors with existing FedTeds logins should be able to use their existing logins. In order to locate solicitation Contractors can go to FedBizOpps and search for the solicitation number at www.fedbizopps.gov. Contractors can register to be put on a plan holders list that others can access through the FedBizOpps site. It is the Offerors responsibility to check the Internet address provided as necessary for any posted changes to this solicitation and all amendments. The non-cost evaluation factors and their importance are listed below: FACTOR 1: PAST PERFORMANCE: This factor is ranked as the highest importance. FACTOR 2: CONTRACT DURATION AND SUMMARY SCHEDULE. This factor is ranked as the second highest importance. Award will be made to an Offeror whose technical submittal and price proposal for the contract contains the combination of those criteria requested offering the best value to the Government. Proposals shall include sufficient detailed information to allow complete evaluation. The Government reserves the right to reject any and all offers. Offerors are reminded that while the Government may elect to consider data obtained from other sources, the burden of proof of acceptability rests with the Offeror. This solicitation will be issued in electronic format only, and will be available on or about August 24th, 2011. Note: Response Date referenced under General Information does not refer to the PROPOSAL DUE DATE. Information on the PROPOSAL DUE DATE will be stated in the solicitation.
- Web Link
-
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA21/W912HN-11-R-0040/listing.html)
- Place of Performance
- Address: Richard B. Russell Dam and Lake 4144 Russell Dam Drive Elberton GA
- Zip Code: 30635-9271
- Zip Code: 30635-9271
- Record
- SN02525091-W 20110810/110808234852-c0b097f0e2dd5d3c34902bca30010c3a (fbodaily.com)
- Source
-
FedBizOpps Link to This Notice
(may not be valid after Archive Date)
| FSG Index | This Issue's Index | Today's FBO Daily Index Page |