AWARD
59 -- Essential Parts Replacement Program
- Notice Date
- 7/5/2011
- Notice Type
- Award Notice
- NAICS
- 334511
— Search, Detection, Navigation, Guidance, Aeronautical, and Nautical System and Instrument Manufacturing
- Contracting Office
- Department of the Air Force, Air Force Materiel Command, Hill AFB OO-ALC, OO-ALC/PKXB, 6038 Aspen Ave (Bldg 1289), Hill AFB, Utah, 84056
- ZIP Code
- 84056
- Solicitation Number
- FA8217-10-R-51078-0001
- Point of Contact
- Randy C. Singleton, Phone: 8015861229
- E-Mail Address
-
randy.singleton1@hill.af.mil
(randy.singleton1@hill.af.mil)
- Small Business Set-Aside
- N/A
- Award Number
- FA8217-11-C-0005
- Award Date
- 6/21/2011
- Awardee
- Lockheed Martin Corporation dba MS2 Radar Systems, 497 Electronics Pkwy Bldg. 5<br />, Liverpool, New York 13088-6062, United States
- Award Amount
- $16,682,712 plus priced options of $72,986,824 for a total of $89,669,536
- Description
- The AEWS long range radar (AN/FPS-117(V)1/4) Essential Parts Replacement Program (EPRP) contract is to replace four main sub-assemblies on the system: the radar data processing cabinets, the platform electronics cabinet, the IFF beacon electronics, and the maintenance control systems (MCS). The EPRP acquisition provides for a basic contract effort of twenty nine (29) radar and beacon modification kits and five (5) MCS modification kits. The following assemblies will be replaced at each radar location: In the Tower Equipment Room: Preprocessor (11A1 cabinet) Moving target indicator processor (11A2 cabinet) Power supplies (11A3 cabinet) Doppler processor (11A4 cabinet) Radar data processor (11A5 cabinet) In the Antenna Platform Electronics (PE) cabinet: Frequency generator/Exciter Logic bucket Radio Frequency (RF) circuit boards Wiring, cabling, interconnections Power supplies / Voltage regulators as recommended IFF beacon electronics All radar system interconnecting cables Digital Electronic Corporation (DEC) Alpha workstation and associated printer All networking/communications hardware Modification or replacement of Tower Equipment Room (TER) Environmental Control System The following will be replaced at each (MCS) center: All system workstationsServers Printers All networking/communications hardware The 29 radar and beacon modification kits and 5 MCS kits will be installed at the following locations: 1 radar and beacon kit plus 1 MCS kit: Hill AFB, UT 15 radar and beacon kits plus 1 MCS kit: various locations in Alaska 11 radar and beacon kits plus 1 MCS kit: various locations in Canada 1 radar and beacon kit plus 1 MCS kit: Mt. Kokee, Hawaii 1 radar and beacon kit plus 1 MCS kit: Punta Salinas, Puerto Rico The delivery schedule is as follows: 18 Months after contract award: radar, beacon, and MCS kit at Hill AFB, UT 20 Months after written notice of option exercise: first four radar kits, first two beacon kits, and MCS in Alaska 24 Months after written notice of option exercise: balance of radar, beacon, and MCS kits The period of performance will be approximately five years
- Web Link
-
FBO.gov Permalink
(https://www.fbo.gov/spg/USAF/AFMC/OOALC/Awards/FA8217-11-C-0005.html)
- Record
- SN02489342-W 20110707/110705234154-7514bb64752d3ded416aadea89decd2b (fbodaily.com)
- Source
-
FedBizOpps Link to This Notice