SPECIAL NOTICE
Y -- RECOVERY--Y--PROJECT NUMBER A1775, Exterior Repairs, Bldg 20, U.S.A.S.S.C., Natick, MA.
- Notice Date
- 12/13/2010
- Notice Type
- Special Notice
- NAICS
- 238110
— Poured Concrete Foundation and Structure Contractors
- Contracting Office
- USACE District, New England, 696 Virginia Road, Concord, MA 01742-2751
- ZIP Code
- 01742-2751
- Solicitation Number
- W912WJ-10-C-0009-P00001
- Archive Date
- 3/13/2011
- Point of Contact
- Elandria M. Cameron, 9783188051
- E-Mail Address
-
USACE District, New England
(elandria.m.cameron@usace.army.mil)
- Small Business Set-Aside
- N/A
- Description
- JC-001, Change Flashing, Delete CMU, Additional Crack Repair Pursuant to the clause of this contract entitled "changes", provide all plant, labor, material and equipment to: A.Change the size of the copper flashing from 20-oz to 16-oz. B.Delete the removal of the second block above the flashing. C.Increase the estimated quantity of crack repair from 1,000 linear feet to approximately 1,591 linear feet. JC-013, Delete Paint/Multiple Changes Pursuant to the clause of this contract entitled "changes", provide all plant, labor, material and equipment to: A.Delete the paint on the exterior of the building. B.Install a reinforced, translucent tarp over the entire East and West walls. Cut out for 3 doors, the louvers in the Boiler Room and the two windows in the bathrooms. Secure the tarps using 2x4 and strapping to prevent the tarp from coming off during the winter. Caulk seams, edges and openings. Remove the tarps, caulking and wood in the spring, infill holes. Provide 8 man-hours per month for 4 months, (32 man-hours total) to maintain the tarp though the winter. C.Perform fifteen (15) tests for asbestos in the existing caulking around the windows and doors on the north, south, east and west walls. Remove and abate the caulking on the Boiler Room window and louver. D.At the Boiler Room window, remove the existing bond beam and install a new lintel, block, flashing and weeps At the Conference Room window, remove the existing bond beam and install a new lintel, block, flashing and weeps. E.Remove and replace 10 damaged CMU block. F.In the Mechanical Room, remove and replace the existing shut-off valve for the exterior hydrant.
- Web Link
-
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA33/W912WJ-10-C-0009-P00001/listing.html)
- Record
- SN02343168-W 20101215/101213233927-117cc988d82539dc586d7be2ba0f4015 (fbodaily.com)
- Source
-
FedBizOpps Link to This Notice
(may not be valid after Archive Date)