99 -- Question and Answers Recieved by 7/19/2010Posted 7/21/2010; WTP Sediment/Sludge Removal

Notice Date
7/21/2010
 
Notice Type
Modification/Amendment
 
NAICS
562219 — Other Nonhazardous Waste Treatment and Disposal
 
Contracting Office
RDECOM Contracting Center, Aberdeen Installation Contracting (RDECOM-CC), Directorate of Contracting, 4118 Susquehanna Avenue, Aberdeen Proving Ground, MD 21005-3013
 
ZIP Code
21005-3013
 
Solicitation Number
W91ZLK-10-T-0267
 
Response Due
7/23/2010
 
Archive Date
9/21/2010
 
Point of Contact
Chanel D. Williams, 410-278-0771
 
E-Mail Address
RDECOM Contracting Center, Aberdeen Installation Contracting (RDECOM-CC)
(chanel.d.williams@us.army.mil)
 
Small Business Set-Aside
Total Small Business
 
Description
Questions Submitted 7/14/10-7/19/2010: Question 1: What was the value of the previous contract? Answer 1: The previous contract was separated into 2 contracts. An offical FOIA Request is required for the information. Question 2: For the Sediment Removal estimate of 816, 666 gallons, what is the percent solid on this material? Answer 2: The sediment from the water plant does not need percent solids tested. The liquid sludge from the wastewater plant is acceptable up to and including 15% solids. Question 3: Is there a bid form for this synopsis/solicitation or are we to draw up a proposal? Answer 3: No, this is a combined synopsis/solicitation as such proposal should respond to the PWS and the information in the combined synopsis/solicitation. Question 4: What time of year in the past has this contract taken place and is Item 1 and 2 done at the same time? Answer 4: The water treatment plant is usually performed in the spring and/or fall months. The wastewater sludge can be performed anytime of the year, however the COR would never schedule both operations at the same time. The operations may be performed back-to-back. Question 5: What is the time frame you would like to have the hauling done for Item 1 and 2? Answer 5: At the water plant the entire operation may take up to two weeks to perform. At the wastewater plant, due to travel time, the sludge removal may take 2 to 4 weeks to perform. Question 6: What is the current site for disposal/incineration of the sludge/sediment? Answer 6: The water sediment is spread onto a farmer's field in Harford County. The wastewater sludge is transported to Delaware County Regional Water Control Authority, PO Box 999, Chester, PA 19016.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/notices/1ea21300dc6b0f601f68dc80e29b7c88)
 
Place of Performance
Address: RDECOM Contracting Center, Aberdeen Installation Contracting (RDECOM-CC) Directorate of Contracting, 4118 Susquehanna Avenue Aberdeen Proving Ground MD
Zip Code: 21005-3013
 
Record
SN02212766-W 20100723/100721235049-1ea21300dc6b0f601f68dc80e29b7c88 (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.